Difference between revisions of "IS480 Team wiki: 2012T2 Team Phoenix Milestones"
Jump to navigation
Jump to search
Line 46: | Line 46: | ||
|} | |} | ||
+ | ==Final Schedule & Milestone== | ||
+ | [[Image:Project Schedule latest.png]] | ||
+ | |||
==Proposed & Actual Schedule Comparison (Midterm)== | ==Proposed & Actual Schedule Comparison (Midterm)== | ||
[[Image:Phoenix_timeline.jpg]] | [[Image:Phoenix_timeline.jpg]] |
Revision as of 16:58, 23 April 2013
HOME | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Final Schedule & Milestone
Proposed & Actual Schedule Comparison (Midterm)
Project Schedule & Milestones (Pre-Midterm)
Our project schedule is based on iterative process where we breakdown each iteration by subsets of requirements. Below is the detail of each iteration process.
- Iteration 0 - Getting Started
- Requirement Gathering
- Technology Research
- Scope and Stakeholder Confirmation
- Iteration 1
- Setup Development Environment
- Home Page Design
- Navigation Bar & Logic Design
- Login + Logout
- Create New CCA
- Browse Available CCA
- Iteration 2
- Join CCA
- Approve Join CCA
- User Access Rights
- Prototype for Titanium iOS App
- Manage CCA Members
- Delete CCA Members
- Search CCA Based on Title & Keyword
- Browse CCA Based on Category
- Iteration 3
- Create Banner/Slider
- Manage Banner/Slider
- Usability Test 1
- User Acceptance Test 1
- Iteration 4
- Backend Simulation of OASIS Facility Booking (Database + Web Service REST,JSON)
- Browse Room
- Create Room Booking
- Confirm Room Booking
- Cancel Room Booking
- Push Notification
- Iteration 5
- Wayfinder UI Skeleton
- Map X-Y Coordinates on floorplan