Schedule Metrics
The objective of Team Phoenix's Schedule Metric is to track overall progress of Team Phoenix and discuss appropriate action(s) when necessary.
Points Calculation:
[Actual Number of Days] / [Planned Number of Days] to get a percentage point. Point that was calculated will determine the actions based on the mitigation strategy below.
Iteration 0 Schedule Metric - Updated per 4 November 2012
Iteration 1 Schedule Metric - Updated per 6 November 2012
Bug Metrics
Currently Identified Bug
- Xcode Certificate (Inability to deploy to iPhone device (Found 29/10, Solved 02/11)
- Login UI is not connected to Main Menu (Found 02/11, Solved 04/11)