=== Metrics === | === Metrics === | ||
==== Schedule Metrics ==== | ==== Schedule Metrics ==== | ||
+ | {| cellpadding="9" style="border: 1px solid darkgray; text-align: center; height:50px" | ||
+ | |scope="row" width="1200" style="text-align: left; background: #F5F5F5"| | ||
+ | |||
+ | The diagram below shows the burn-down charts of the 13 sprints we have completed: <br /> | ||
+ | |||
+ | '''Links'''<br> | ||
+ | '''1. [https://wiki.smu.edu.sg/is480/2012T2_Team_Chm:_Project_Management#Schedule_Metric Schedule Metric Calculation]<br /> | ||
+ | '''2. Schedule Metric Documentation for Sprint Number:''' | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=26 1], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=11 2], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=13 3], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=12 4], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=20 5], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=22 6], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=21 7], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=23 8], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=24 9], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=28 10], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=29 11], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=31 12], | ||
+ | [https://docs.google.com/spreadsheet/ccc?key=0AgEVT7COZGKGdDA5cFlXVEMxZVY3Qjc4R29kbnRlTkE#gid=32 13] | ||
+ | |||
+ | <br> | ||
+ | <big><big>'''Release Burn-down Chart'''</big></big><br><br> | ||
+ | [[Image:ReleaseBurndown.png|525px]]<br /><br /> | ||
+ | <big><big>'''Burn-down Charts'''</big></big><br><br> | ||
+ | [[Image:Burndownchart1.png|525px]] | ||
+ | [[Image:Burndownchart2.png|525px]] | ||
+ | [[Image:Sprint91.png|255px]] | ||
+ | <br><br> | ||
+ | |||
+ | |} | ||
+ | |||
==== Bug Metrics ==== | ==== Bug Metrics ==== | ||
=== Technical Complexity === | === Technical Complexity === |
Revision as of 21:43, 17 April 2013
FINAL WIKI |
Project Progress Summary
Final Presentation Slides |
|
Project Highlights
EVENT | HIGHLIGHT / ISSUE |
---|---|
Sprint 11 |
Social Influence Quantification - Algorithm to quantify the effect of Social Messages |
Sprint 11 - 13 |
Sponsor unavailability |
Project Challenges
EVENT | HIGHLIGHT / ISSUE |
---|---|
Social Influence Quantification |
|
User Acceptance Testing |
|
Project Management
Project Schedule (Planned VS Actual)
No changes to proposal and acceptance milestones; and only milestones after them have significant changes to the schedule.
Refer to the current timeline for more information.
Change #1: An additional User Testing, for data gathering needed for our BI tool has been added
Change #2: Part of the Manage Hook function has been shifted over to past mid terms
Change #3: Part of the Manage Insights has been shifted to before mid terms
Metrics
Schedule Metrics
The diagram below shows the burn-down charts of the 13 sprints we have completed: Links |
Bug Metrics
Technical Complexity
The technical complexities of our tools employed are in the following descending order:
COMPLEXITY | DESCRIPTION |
---|---|
Creation of Social Message Hooks |
|
Tracking of Social Message Views |
|
Magento Community Edition |
|
D3.js Data Manipulation Framework |
|
jQuery UI Framework |
|
Foundation Framework by ZURB |
|
Quality of Product
Project Deliverables
Stage | Specification | Modules |
---|---|---|
Project Management | Minutes | |
Metrics | ||
Requirements | Product Backlog | |
UI Mockups | ||
Analysis | Use Case | |
Design | ER Diagram | |
Server Architecture | ||
Testing | User Testing 2 Plan | |
User Acceptance Test |
Quality
Deployment
- Staging & Development Environment: deployed on GoDaddy server
- Database: Magento EAV database structure
- Web Links:
User Acceptance Test (UAT)
Objectives
Test Details & Outcome
Reflections
Individual Reflections
Sponsor Comments
"We believe that Mobisupermarket will transform the way marketing trainees and IT systems interact, providing these trainees with an efficient alternative to the traditional data analytics."
|