PROJECT SCHEDULE MILESTONES RISK METRICS DELIVERABLES


Schedule Metrics

Aim: To track the progress of development for each iteration.
Formula: Schedule Metric = Estimated Duration / Actual Duration
Schedule Metric1.jpg

Our current schedule metric

File:Schedule Metric 2

File:Schedule Metric 1


Bug Metrics

Aim: To identify the number of bugs in each iteration and take respective plans for quality assurance.
Formula: Identifying the severity level of the bug
DC Bug Matrix.png
DC Bug Matrix 1.png

To view our bug metric :