===='''Individual Efficiency Metric'''====
 
===='''Individual Efficiency Metric'''====

Revision as of 12:51, 21 February 2013

Welcome to DaDa Achievers FYP Wiki!
Home Project Overview Project Management Project Documentation Project Progress Summary Reflections


Project Management

Project Schedule

DaDaTimeline v5.PNG


Iteration No. Description Progress (%)
1 Authorization, add/delete/update product and show product status 100%
2 Barcode creation and scanning 60%
3 Inventory tracking 100%
4 Online ordering, order request and order tracking 100%
5 Update order and process payment 100%
6 Inventory Management System and E-commerce Internal Testing 100%
7 Customer Records Management 90%
8 Usability Testing 1 100%
9 Import/Export wizard for excel 100%


Detailed project schedule with comparison between planned and actual duration can be found over the link: Detailed Project Schedule-DaDa Achievers

Project Metrics

Schedule Metric

Goal: We want to improve upon overall project task completion time
Question: How accurate are my schedule estimates?
Metric Score (X): Actual Duration / Estimated (Planned) Duration
Usage: Refer to table below

Metric Score Action Plan
X < 0.7
Project is way ahead of schedule.
PM to decide whether to revisit project scope, and explore more functions to include.
0.7 ≤ X < 0.9
Project is slightly ahead of schedule.
No re-scoping necessary. Channel excess time into testing.
0.9 ≤ X ≤ 1.1
Project is on schedule.
1.1 < X ≤ 1.3
Project is behind schedule.
PM to work with team to redeploy and possibly re-adjust schedule to increase length of iteration.
X < 1.3
Project is severely behind schedule.
PM to communicate problems for delay to stakeholders, and if necessary, discuss and agree upon a reduction in project scope.

DaDaScheduleMetricsnew.GIF

Individual Efficiency Metric

Goal: To ensure that each team member’s skills are utilized which leads to greater team productivity. This in turns leads to complementing the project planning and task completion rate.

Frequency of measurement: At the end of every iteration/phase

Formula of individual productivity coefficient:
• Individual EC = Actual duration of allocated task/ planned allocated duration of each task to each member.

• Average Individual AEC = Sum of EC of each team member / number of tasks allocated


Average Individual Efficiency Coefficient (AEC) Score Observation Action Plan

AEC < 1

Very efficient and finishes tasks slightly ahead of time.

Start next task earlier or PM to allocate lesser hours for subsequent tasks.

AEC = 1

Task duration planning is accurate.

None required. Team member is efficient in completing his/her task on time.

1 < AEC ≤ 2

Team member is a slightly behind estimated schedule.

Acceptable. An additional 12 hours are given to the member to finish up the task.

2 < AEC

Team member is too far behind schedule or PM has estimated too short a duration for the allocated tasks.

Bad. The team member had exceeded the planned duration for more than 35%.
The project manager will either assign another teammate to assist in finishing the task or to arrange for an ad-hoc meeting to solve the problem.

Bug Metric

Goal: We want to improve the software quality of our product
Question: What are the bugs that occur during development, what are their impact and how will they affect the overall project schedule?
Frequencey of measurement: At the end of every iteration
Bug Severity Index (BSI) Total = 1 x num (low) + 5 x num (high) + 10 x num (critical)

Severity Description

Low Impact (1 points)

Occurs due to typo error or minor code errors with the system logic.

High Impact (5 points)

The inventory management and e-commerce system runs but certain functions are broken.

Critical Impact(10 points)

The server or database is unstable and the e-commerce site is down

Action plan

DaDaBugMetrics.GIF
BSI Action
Points =< 5 Fix during development time only.
5 < Points< 10 PM to assign other team members to help out in debugging.
Points>=10

The current iteration will be put on hold. The PM will need to make adjustments to the project schedule
The PM will also have to call for an urgent meeting with the team to reassess severity and work out an solution.

Project Risks

Classification Risk Description Impact Probability Mitigation Strategy and Triggers (if applicable) Status, and Remarks (if any)
Technology Unfamiliarity of Flash technology for development of the Ring Customization tool High High Allocate time for adequate learning as well as approaching people with relevant experience, if possible, for guidance. Risk have not occurred yet
Technical & Learning Risk Delay of prototype development due to technical challenge High Medium Trigger: Schedule Delay
Initiate research on any technologies that would be easier to implement, and if possible, produce a prototype to confirm the technology switch.
Controlled
The team plans to firm up technology decisions via working prototypes by week 2.
Technology Over-reliance on 3rd Party API such as PhoneGap and E-nets High Medium Conduct proper research and seek alternatives Followed Mitigation Strategy:
Implemented Paypal instead of E-nets
Project Management Client is resistant to change of business processes and adoption of new technologies Medium Low Conduct thorough analysis and provide a concise solution. Walk client through the needs for such changes. Controlled
We have met up with the client several times to review the proposed solution and changes.
Project Management Scope creep: Client requests to add on functions above and beyond what was agreed upon Medium Low Perform thorough requirements analysis and create a baseline. When change is required, PM will meet with the team and compare against baseline and project schedule to see if change can be allowed. Risk have not occurred yet
Resolved Risks

Technologies Used

Technology used v2.PNG