Difference between revisions of "IS480 Team wiki: 2012T2 Can.One Midterm"
Jump to navigation
Jump to search
Line 96: | Line 96: | ||
===Schedule Overview=== | ===Schedule Overview=== | ||
− | [[Image:Can.One Schedule.png| | + | [[Image:Can.One Schedule.png|left|1050px]] |
<br> | <br> | ||
---- | ---- |
Revision as of 22:09, 20 February 2013
Home | Project Overview | Project Management | Project Documentation | Testing | Learning Outcome |
CAN.ONE Midterm Page
click for midterm presentation slides
Project Progress Summary
Project Highlight
⇒ Completed 8 iteration (total: 11 iteration)
⇒ Buffer time:
- → 2 days buffer at the end of every iteration
- → 1 week buffer at the end of every 2 iterations
⇒ Finish 70% of project
⇒ Conducted 1 User Testing
⇒ Meeting (22 internal, 13 sponsor, 11 supervisor)
Project Management
Project Scope
Planned
No. | Main Feature | Component | Description |
1 | User Management | Registration, Login, Profile | Enhance users' register and login experience.
Manage users' personal details. |
2 | 3D Visualization | 2D Photo to 3D Avatar | Implement A*Star technology which allows rendition of 2D photograph to 3D picture. |
3 | Shopping | Catalog, Purchase, Try On Product, Past Purchases, Payment Gateway, Order Status | Create an e-commerce application to ease users' shopping process. |
4 | Social | Friends, Chat, Group, Group Chat | Social network features which allow user to interact with one and another. |
5 | Recommendations | User Data, Others' Purchase Pattern | Provide personalized recommendation for each user based on user input and advanced tracking. |
Actual
Those highlighted in blue are new task that was previously not in the project scope
Schedule Overview
Schedule Overview (Planned vs Actual)