IS480 Team wiki: 2012T2 Can.One Final
Revision as of 02:17, 16 April 2013 by Gracelee.2010 (talk | contribs) (→Intermediate Deliverables)
Home | Project Overview | Project Management | Project Documentation | Testing | Learning Outcome |
CAN.ONE Final Page
Project Progress Summary
Project Highlight
⇒ Finish 100% of project (11 iterations)
⇒ Buffer time:
- → 2 days buffer at the end of every iteration
- → 1 week buffer at the end of every 2 iterations
⇒ Conducted 3 Usability Test and 3 User Acceptance Test
⇒ Meeting (30 internal, 16 sponsor, 14 supervisor)
⇒ Additional features:
- → Vendor Portal
- → Enhanced 3D Avarar Interaction
⇒ Dropped features:
- → Recommendation Based on Chat
- → Club
Completed Features (Post-Midterm)
Project Management
Project Scope
Planned
No. | Main Feature | Component | Description |
1 | User Management | Registration, Login, Profile | Enhance users' register and login experience.
Manage users' personal details. |
2 | 3D Visualization | 2D Photo to 3D Avatar | Implement A*Star technology which allows rendition of 2D photograph to 3D picture. |
3 | Shopping | Catalog, Purchase, Try On Product, Past Purchases, Payment Gateway, Order Status | Create an e-commerce application to ease users' shopping process. |
4 | Social | Friends, Chat, Group, Group Chat | Social network features which allow user to interact with one and another. |
5 | Recommendations | User Data, Others' Purchase Pattern | Provide personalized recommendation for each user based on user input and advanced tracking. |
Actual
Schedule Overview
Schedule Overview (Planned vs Actual)
Schedule Change
|
|
Project Metrics
Schedule Metric
Schedule Metric Score
Bug Metric
Bug Tracking Log
Click here to check out our bug list!
Bug Tracking Chart
Quality of Product
Intermediate Deliverables
Stage | Specification | Modules |
---|---|---|
Project Management | Minutes | |
Requirements | User Requirement | |
Analysis | Use Case | |
Pre-Acceptance Survey | ||
Design | Deployment Diagram | |
Resources & Framework | ||
UI Mockups | ||
Logical Diagram | ||
Testing | User Testing | |
System Testing |
Deployment
Steps:
- Communicate with Sponsor – ask them to register for an Azure account
- Use Sponsor’s account to add us as developer
- Create database and website on Windows Azure
- On the project itself - configuration (mostly on DB – e.g. DB connection string, DB services)
- Must make sure that the configuration is within pricing range
Technical Complexity
⇒ Steep learning curve in working with the XMPP server
⇒ Enabling HTTP Proxy access to Openfire server and integrate it to enable ASP.NET
⇒ Constantly changing interface design (feedback from UT & Sponsor)
⇒ 3D Rendering and Controls
- → Rendering transparent materials
- → Environment
- Lighting
- Camera Perspective
- → User interaction
- Rotation
- Zoom
- Add/remove products from head avatar