Charting the Project Milestones



The milestones for the project is shown as follows:
Chapter names and StoryIDs are referenced from the Product Backlog.


Milestone Goals and Features Completed End Date
1 a. Project Initialisation

- Setting up of development environment

- Researching and developing tutorials for team members

- Knowledge sharing sessions by Tech and UI Lead


b. Proof-Of-Concepts

Complete:

- StoryID: S12, S15


c. Complete Phase 1

Complete:

- Chapter: Manage Landing Page

- Chapter: Manage Account

- Chapter: Manage Portfolio

- Chapter: Manage Experience

- StoryID: S21-S24 (from Chapter: Manage Casting Calls)

- StoryID: S55-S56 (from Chapter: Manage Search)


d. Complete Project Acceptance

13 AUG 2012
2 a. Phase 2

Complete:

- Chapter Manage Application

- StoryID: S26-S27 (from Chapter: Manage Casting Calls)

- StoryID: S59-S62 (from Chapter: Manage Search)


b. Usability Testing 1

9 SEP 2012
3 a. Phase 3

Complete:

- Chapter Manage Messages

- StoryID: S25, S28, S29, S30, S31, S32 (from Chapter: Manage Casting Calls)

- StoryID: S57-S58 (from Chapter: Manage Search)


b. Mid-term presentation

1 OCT 2012
4 a. Phase 4

Complete:

- Chapter Manage System


b. Usability Testing 2

26 OCT 2012
5 Finalize Project and Complete Final Presentation/submission 26 NOV 2012