HeaderSIS.jpg

Difference between revisions of "IS480 Team wiki: 2012T1 Timber Werkz"

From IS480
Jump to navigation Jump to search
Line 107: Line 107:
 
| style="border:none"  |
 
| style="border:none"  |
 
! scope="col" width="150" style="height:130px; background: #ffdead;" |
 
! scope="col" width="150" style="height:130px; background: #ffdead;" |
<big><big>21 SEP 2012</big></big>
+
<big><big>TBC</big></big>
 
<br>''with Supervisor''
 
<br>''with Supervisor''
  

Revision as of 11:32, 1 October 2012

HOME   PROJECT OVERVIEW     PROJECT MANAGEMENT   DOCUMENTATION  
         


<< MID-TERM WIKI

Greetings

TwTeam3.jpg


A warm welcome to the TimberWerkz Main page!

Our team is developing an audition portal named Casting3 for our Client - Oak3Films.
This page provides a summary of the latest events and the progress of our development process.


Crystal Clear action bookmark.png       1. Visit our Mid-Term Wiki
2. Sign up as a new user @ our Casting3 Development Site


Notifications


TwLogo2.jpg
Current Sprint Upcoming Meetings Running Towards


8
Duration:
(22 SEP - 3 OCT)

TBC
with Supervisor

TBC
with Client


4th

Milestone:
(Mid Term, 5 OCT)












Latest Events


DATE EVENT
21 SEPT 2012 Supervisor Meeting 5:
14 SEPT 2012 Supervisor Meeting 4:
7 SEP 2012 Usability Test 1
Back to Top

Project Progress


Milestone 4 (Current)

Milestone Goals to Complete Status
#4
Mid Term

01 OCT 2012
1. Manage Portfolio
  • Set featured video
  • Add experience
Developing
2. Manage Casting Calls
  • Schedule an Interview
Developing
3. Manage Applications
  • Confirm audition availability
Developing


Milestone 3

Milestone Goals to Complete Status
#3
Usability Test 1

09 SEP 2012
1. Manage Casting Call
  • Invite artiste to audition
  • View applicants
Completed
2. Manage Applications
  • Submit Application
  • View Application
  • Update Application
  • Withdraw Application
Completed
3. Manage Portfolio
  • Production House Portfolio
Completed