Line 130: | Line 130: | ||
! scope="col" width="820" | EVENT | ! scope="col" width="820" | EVENT | ||
|- | |- | ||
+ | ! scope="row" | '''14 SEPT 2012''' | ||
+ | |style="text-align: left;"| ''' Supervisor Meeting 4: ''' | ||
+ | *Update on Usability Test 1 | ||
+ | *[https://docs.google.com/document/d/1GdfzrQ537LyQn1_37s5LJeyACsoi7mynJcow5vFaB60/edit Supervisor Meeting Minutes 4] | ||
+ | *[https://docs.google.com/file/d/0BwXGnbL-305eQWJnRGxtQ2dVTzg/edit Presentation Slides] | ||
! scope="row" | '''7 SEP 2012''' | ! scope="row" | '''7 SEP 2012''' | ||
Line 145: | Line 150: | ||
*[https://docs.google.com/document/d/1gMkUCO38BsIKaXiavhwIXMqTH6WSAjfJ17mKBJGQT4U/edit Supervisor Meeting Minutes 3] | *[https://docs.google.com/document/d/1gMkUCO38BsIKaXiavhwIXMqTH6WSAjfJ17mKBJGQT4U/edit Supervisor Meeting Minutes 3] | ||
*[https://docs.google.com/presentation/d/1clXBl1JXc9LcJvA7fvKoAGW8mDn-EUkPn4wXDWcjpaM/edit#slide=id.p18 Presentation Slides] | *[https://docs.google.com/presentation/d/1clXBl1JXc9LcJvA7fvKoAGW8mDn-EUkPn4wXDWcjpaM/edit#slide=id.p18 Presentation Slides] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
|} | |} | ||
Revision as of 12:26, 14 September 2012
HOME | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Greetings
A warm welcome to the TimberWerkz Main page!
Our team is developing an audition portal named Casting3 for our Client - Oak3Films.
This page provides a summary of the latest events and the progress of our development process.
Sign up as a new user @ our Casting3 Development Site
Notifications
Current Sprint | Upcoming Meetings | Running Towards | ||||
---|---|---|---|---|---|---|
|
14 SEP 2012
|
TBC
|
4th Milestone: |
Latest Events
DATE | EVENT | ||
---|---|---|---|
14 SEPT 2012 | Supervisor Meeting 4:
|
7 SEP 2012 | Usability Test 1
|
30 AUG 2012 | Supervisor Meeting 3
|
Project Progress
Milestone 4 (Current)
Milestone | Goals to Complete | Status |
---|---|---|
#4 Mid Term 01 OCT 2012 |
1. Manage Portfolio
|
Developing |
2. Manage Casting Calls
|
Developing | |
3. Manage Applications
|
Developing |
Milestone 3
Milestone | Goals to Complete | Status |
---|---|---|
#3 Usability Test 1 09 SEP 2012 |
1. Manage Casting Call
|
Completed |
2. Manage Applications
|
Completed | |
3. Manage Portfolio
|
Completed |