Project Progress Summary

Project Summary

Since started off as a passionate team of 5 in May, we have gone through 4 iterations of construction, learning and verifications. We have strictly followed our core methodology, to Build, Measure and Learn that is adopted from Lean Startup. This methodology not only teaches us to change/pivot when necessary, but also to prevent wastage of efforts and time. Not only do we have to grab every opportunity to verify assumptions, build with leaner resources and learn from results, we have to understand client's needs and handle ever-changing situations.


What we have done thus far:

  • Built the application that can be used to do register with Sageby and create an account, do a survey and to share or feedback to Sageby Surveys
  • Constructed the Application Programming Interface that provides support for User and Survey data retrieval
  • Executed Beta Testing and Live Testing with more than 100 users combined
  • Carried a real survey by LTA that provides real rewards
  • Transitioned from Development Database to Live Database
  • Transitioned from iOS5 to iOS6
  • Deployed twice in Appstore and garnering 80 downloads till date

Project Highlights

Despite having a clear schedule and backed with good responses from Clients, there are still unseen situations that arises and needed our attention to either rectify the problem or grab the opportunity that improves our product.

1 Construction of Application Programming Interface (API)

To receive dynamic data and move beyond a Proof-Of-Concept product, Sageby graciously agreed to help to build the APIs that are necessary. However, their lead developer unforeseeably had to leave Sageby due to personal reasons.We had to make a drastic addition to our schedule by squeezing in time and manpower for building API while removing non-functional aspects such as testing for Performance Profiling and Memory Leaks.

Through this initiative, we managed to build the necessary APIs in time for our Live Test / User Test 3 that is an extremely important milestone in our project.

2 Transition from Development Database to Live Database

Sageby set out numerous stringent tests that we had to comply with before allowing us to access their live database. Thankfully, our diligence paid off and Sageby felt confident with having the application to access the live server.

However, before that, we had to clear several legacy issues such as MySQL plugin versioning issues, different PHP versions and unfortunately, face a database account user lockdown.

After ironing out issues and successful uploading of APIs, we managed to move from dummy data to real users data and this brought us to the next level in product development, from a Proof-Of-Concept to a usable and productive Application!

3 Live Testing with LTA Survey & Real Rewards

After carrying out the transitioning of database and inserting of API queries and codes, we managed to finish our iteration in time for User Test 3. However, Sageby proposed another idea that allows us to carry a real survey by LTA and to give out real rewards. Considering the fact that User Test 3 is targeted at a wider pool of users, we had to make changes to the current UT plan and accomodate the LTA survey.

This inclusion of LTA survey really showed us the true potential of the application as it shows that not only users are fine with doing surveys on mobile, many agreed that a niche type of survey can be dedicated for the mobile platform, Short Survey Polls.

Project Management

Project Timeline

Sageby ProjTimeline midterm.png

Schedule Brief

Sageby schedulebrief.png

Project Status

Task/function/features, etc Status Confident Level Comment
Login Module Fully deployed and tested 100%. However, it is not updated to latest Facebook SDK due to lack of backward compatibility with iOS 5 1 Luojia
Survey Module Fully deployed and tested 100%, with categorization via alphabetical order 1 Luojia
Rewards Module (Store) Fully deployed and tested 100%, with categorization via alphabetical order 1 Luojia
Rewards Module (Wallet) Fully deployed and tested 100%, with categorization via used & unused sections 1 Luojia
Settings Tab Fully deployed and tested 100% 1 JunHao & Mervyn
Social Sharing Module Fully deployed and tested 100% 1 TeeJun
Feedback Channel Fully deployed and tested 100%. Used Apptentive Package for feedbacks and easy rating portal. 1 Junhao
Performance Profiling & Memory Leak Tests Function to be Kept in View. To be continued if necessary. 1 Marcus
Performance Profiling & Memory Leak Tests Function to be Kept in View. To be continued if necessary. 0.5 Marcus
Application Programming Interface Partially developed, deployed and tested 50%. Survey, Users and Rewards Module completed 1 Marcus
Database Transition from Development to Live Fully deployed and tested 100% 0.8 Marcus
Unit Tests Partially developed, deployed and tested 50%. Login, Surveys, Rewards, User Module & Settings tab covered 0.8 JunHao
Facebook Sharing UIView Partially developed, deployed and tested 50%. 1 Mervyn
Mobile Template for Lime Survey Fully deployed and tested 100% 1 Mervyn & Junhao
Social Integration Partially developed, deployed and tested 30%. Twitter integration and Facebook Login 0.8 Luojia

Projet Schedule (Plan VS Actual)

Despite having several additions in our project scope, we managed to narrow down the non-functional requirements of the applications and added an extra week in Iteration 4 to accomodate our User Tests.

Planned Actual
Iteration Task Start End Start End Comment
1 Complete Paper Prototype for client's acceptance 30/5/12 5/6/12 30/5/12 5/6/12
Develop sample iOS App 6/6/12 13/6/12 6/6/12 13/6/12
Complete Prototype with Survey Module 14/6/12 27/6/12 14/6/12 27/6/12
2 Build Facebook Single Sign On Auth 27/6/12 3/7/12 27/6/12 3/7/12
Build Sageby Manual login 3/7/12 11/7/12 3/7/12 11/7/12
Allow user to logout 3/7/12 11/7/12 3/7/12 11/7/12
Build User details popup 11/7/12 17/7/12 11/7/12 17/7/12
Build different in-house survey layouts. Allow survey question to have dynamic survey layout 17/7/12 25/7/12 17/7/12 25/7/12
Able to pull dummy data from Sageby's server 17/7/12 25/7/12 17/7/12 25/7/12
Build survey's question routing function 17/7/12 25/7/12 17/7/12 25/7/12
Deploy and upload to Apple's Appstore 31/7/12 31/7/12 31/7/12 3/8/12 Code-signing error and outdated library links led to 3 days delay in deployment
3 Build browsable table for Store vouchers 1/8/12 8/8/12 1/8/12 8/8/12
Allow users to redeem vouchers 1/8/12 8/8/12 1/8/12 8/8/12
Build browsable table for Wallet vouchers 8/8/12 15/8/12 8/8/12 15/8/12
Build QR generator 8/8/12 15/8/12 8/8/12 15/8/12
Deployment on Appstore 21/8/12 21/8/12 8/9/12 8/9/12 Pushed to Iteration 3 due to the lack of APIs
4 User is able to share completed surveys via Facebook share and Twitter 22/8/12 29/8/12 22/8/12 29/8/12
Users will be able to provide feedbacks to Sageby Surveys 22/8/12 29/8/12 22/8/12 29/8/12
User is able to share referral link for benefits 22/8/12 28/8/12 22/8/12 28/8/12
Build iFrame to support Lime survey 29/8/12 4/9/12 29/8/12 4/9/12 Added an Extra week to support external survey engine
Build iFrame to support Lime survey (Added) 29/8/12 4/9/12 Needed to support external survey engine for live testing(UT3)
Built User & Survey Module's APIs (Added) 5/9/12 11/9/12 Added an Extra week to build APIs to receive dynamic data and prepare for live testing (UT3)
Transitioned from iOS5 to iOS6 (Added) 12/9/12 18/9/12 Added an Extra week to transition from iOS5 to iOS6 in order to update deprecated APIs and to support application on iPhone 5
Transitioned from Development Database to Live Database (Added) 12/9/12 18/9/12 User will be able to register with Sageby and do real surveys.
Deploy to Appstore 25/9/12 25/9/12 30/9/12 30/9/12 Delayed by 5 days due to rejection from Appstore for several unsupported APIs

Project Metrics

We have chosen Schedule Metric and Bug Metric as it best suits a development for iOS due to expected rapid changes in schedule and unforeseen bugginess of a mobile app.

Schedule Metric

Current Standing Sageby pm midterm.png

Issues Faced in Iteration 2

The team managed to complete new tasks on time in iteration 1. However, the technical complexity that we faced in iteration 2 was on a different level and we did not expect to face issues with customized survey styles and Facebook Login. This caused us to push our schedule back by 5 days.

Another issue was the delay of APIs from Sageby. This delay caused us to lose up to another 5 days in testing and development, and we had to hard code dummy data in order to meet the requirements for User test 2 for the iteration.

Issues Faced in Iteration 4

After Iteration 3, we had to re-scope iteration 4 due to several milestones to be met:

  • Move beyond proof of concept
  • Live Testing with real surveys and wide pool of users
  • Allow users to register with Sageby

In iteration 2, we faced numerous issues regarding unknown durations for new tasks. In iteration 4, we revised through these tasks and scope out based on the team's experience with development. We had to add 2 weeks to iteration 4, out of the 3 buffer weeks intended, in order to accomodate 3 other major phases, iOS6, Live Database and construction of APIs.

The schedule metric has been highly useful for us by providing us with an better grasp of our current situation and to track the amount of time we took with difficult tasks. Project Manager was also able to efficient allocate extra time and also to meet up with changing demands and opportunities such as the unexpected chance of deploying a real survey for UT3.

Bug Metric

Current Standing Sageby bug midterm.png

We needed the Bug Metric to answer 3 important questions during development:

  • Where did it originate from
  • Impact of the bug
  • How many are there

With the aid of the Bug Metric, we managed to identify key issues, which includes Facebook Login and sharing and persistent UI Bugs. Coding in Storyboard with Objective-C bypasses the conventional coding of transitions of Views in iOS. This is a huge improvement in convenience for new developers such as us, but when bugs arises, we need to identify the location of it and to rectify the issue by diving into the source codes and make manual changes.

Overall, the Bug Metric shows high correlation with the Schedule Metric and this is a relatively positive indication for the Project Manager that data collected responds well with the different Metrics in use.

Issues faced

Project Risks

We have split the risks into 2 components, Client and Project Management. Client's risk are rather intensive as Sageby is a new startup and they face plenty of risks that we have to take into account. Project Management on the other hand is rather standard but requires clear mitigation plan to avoid confusion within the team.

Client & Project Management

Sageby Risk1 midterm.png

Project Development

Sageby Risk2 midterm.png

Technical Complexity

Technical Complexity takes into consideration of Team Sageby's main development pain points. Although there are other complexities such as Facebook login SDK issues and iOS 6 with backwards compatibility, these issues can be temporarily kept in view due to the immaturity of the SDK and platforms.

Sageby Technical complexity midterm.png

Quality of Product

Sageby Surveys formally launched on 18th of September and it comes with a full fledged working survey module which allows users registration with Sageby. The quality of product mentioned below focuses more on the non-functional aspects of the Application as functional tasks list are stated in the project scope. Also, these deliverables are constitutes the structure of the application and ensure its integrity and development modularity.

Sageby Qualityofproduct midterm.png

Intermediate Deliverables

Stage Specification Modules
Project Management Meeting Minutes Team meetings: Minutes 1-12
Supervisor: Minutes 1-7
Requirements Mid Term Presentation Mid Term Presentation Slides
Analysis Use case Use Case Diagram & Documentation
Service Diagram Service Diagram
Design Architecture System Diagram System Architecture
ER Diagram ER Diagram
UAT 1 Documents UAT 1 Test Plan UAT 1 Test Plan
UAT 1 Test Introduction, Survey Questions and initial Test Case UAT 1 Test Introduction, Survey Questions and initial Test Case
UAT 1 Results and Analysis UAT 1 Results

Deployment

  • Sageby Surveys Version 1.1 is currently deployed on Appstore
    • Garnered 80 downloads
  • API is deployed on Sageby Dev Server but connected to Sageby Live Database
    • Backup on Sageby Dev Database
  • Development Application is provisioned on 5 iPhones within the team
    • Provisioned 1 iPhone that is with Sageby

Testing

Unit Testing

Automated Testing

Reflection

Our Team has gone through 4 iterations, from scoping, to planning, prototyping, constructing and carrying User Test.

Team Reflection