Description
|
Duration
|
Risk Level
|
Action Taken
|
Team member is sick or on medical leave.
|
< 3 days
|
Low
|
Project manager may assign stand-in member to do the member’s assigned work.
|
|
3 – 7 days
|
Low
|
Project manager assign stand-in member to do the sick member’s assigned work.
Reschedule of project schedule may be required.
The stand-in member assigned to take over the work temporarily must update the progress to that member responsible.
|
|
> 7 days
|
Low
|
Project manager have to reassign and redistribute workload among other team members.
Reschedule of project schedule may be required.
The stand-in member assigned to take over the work temporarily must update the progress to that member responsible.
|
Team member has to rush for assignment due or has a major quiz for other modules.
|
< 3 days
|
Moderate
|
Project manager may assign stand-in member to do the member’s assigned work.
|
|
3 – 7 days
|
Moderate
|
Project manager assign stand-in member to do the sick member’s assigned work.
Reschedule of project schedule may be required.
The stand-in member assigned to take over the work temporarily must update the progress to that member responsible.
|
Team member has other commitments in the midst of the project
|
< 3 days
|
Low
|
Project manager may assign stand-in member to do the member’s assigned work.
|
|
3 - 7 days
|
Moderate
|
Project manager have to reassign and redistribute workload among other team members.
Reschedule of project schedule may be required.
The stand-in member assigned to take over the work temporarily must update the progress to that member responsible.
|