Detailed Schedule

Functions Key Personnel Plan Schedule Actual Schedule Remarks
Planning 7 May - 19 July 7 May - 19 July
  • Project Brain Storming/ Looking for Suitable Clients
All 7 May - 28 May 7 May - 28 May
  • Preparation of Project Proposal
All 29 May - 19 June 29 May - 19 June
  • Documentation and Design
All 19 June - 19 July 19 June - 19 July


Iteration 1 19 July - 31 July 19 July - 2 Aug
Documentation
  • Update Use Case
Zou Mei 19 July 19 July Completed
  • Update Domain Diagram
Shoe 19 July 19 July Completed
  • Create Test Cases for Tag and Bag Plugin
Jasmine 19 July 19 July Completed
Development
Tag and Bag Plugin Zhen Guang 85% Completed
  • Information Extraction
20 July - 28 July 20 July - 29 July
  • Error Reporting
20 July - 28 July Not Completed Shift to Iteration 8
  • Session Cart
20 July - 28 July 20 July - 29 July
Unit Testing
  • Testing
Zou Mei 29 July 31 July Completed
  • Document Test Cases
Qian Hwee 29 July 31 July Completed
Integration
  • Debugging
Zhen Guang 30 July 1 Aug Completed
Deployment
  • Testing
Shoe 31 July 2 Aug Completed
  • Document Full Test Cases
Jasmine 31 July 2 Aug Completed
Buffer 1 Aug - 2 Aug 2 Buffer day used
Iteration 2 3 Aug - 10 Aug 3 Aug - 10 Aug
Documentation
  • Update Use Case
Qian Hwee 3 Aug 3 Aug Completed
  • Update Domain Diagram
Jasmine 3 Aug 3 Aug Completed
  • Create Test Cases for Internal Portal
Zou Mei 3 Aug 3 Aug Completed
Development
User Management Ryan Completed
  • Login & Logout
4 Aug - 6 Aug 4 Aug - 6 Aug
  • Create Account
4 Aug - 6 Aug 4 Aug - 6 Aug
Cart Management Zhen Guang, Qian Hwee Completed
  • View Items
4 Aug - 6 Aug 4 Aug - 6 Aug
  • Delete Items
4 Aug - 6 Aug 4 Aug - 6 Aug
  • Add Items to Spree
4 Aug - 6 Aug 4 Aug - 6 Aug
  • Calculation of Item Costs
4 Aug - 6 Aug 4 Aug - 6 Aug
  • Check Out
4 Aug - 6 Aug 4 Aug - 6 Aug
Unit Testing
  • Testing
Shoe 7 Aug 7 Aug Completed
  • Document Test Cases
Zou Mei 7 Aug 7 Aug Completed
Integration
  • Integration
Zhen Guang 8 Aug - 9 Aug 9 Aug Completed
  • Debugging
Ryan 8 Aug - 9 Aug 9 Aug Completed
Deployment
  • Testing
Jasmine 10 Aug 10 Aug Completed
  • Document Full Test Cases
Shoe 10 Aug 10 Aug Completed
Buffer 11 Aug - 12 Aug
Iteration 3 13 Aug - 24 Aug 13 Aug - 26 Aug
Documentation
  • Update Use Case
Shoe 13 Aug 13 Aug Completed
  • Update Domain Diagram
Zou Mei 13 Aug 13 Aug Completed
  • Create Test Cases for User Management
Jasmine 13 Aug 13 Aug Completed
Development
Organiser User Management Qian Hwee, Ryan Completed
  • Organiser Account Verification
14 Aug - 20 Aug 14 Aug - 20 Aug
  • Forget Password
14 Aug - 20 Aug 14 Aug - 20 Aug
  • Delete Account
14 Aug - 20 Aug 14 Aug - 20 Aug
  • Update Account Details
14 Aug - 20 Aug 14 Aug - 20 Aug
  • User Profile
14 Aug - 20 Aug 14 Aug - 20 Aug
Tag and Bag Plugin
  • Drag and Drop from Site Plugin
Zhen Guang 14 Aug - 20 Aug 14 Aug - 23 Aug Newly Added - Completed
Unit Testing
  • Testing
Jasmine 21 Aug 24 Aug Completed
  • Document Test Cases
Shoe 21 Aug 24 Aug Completed
Integration
  • Integration
Zhen Guang 22 Aug - 23 Aug 22 Aug - 25 Aug Completed
  • Debugging
Ryan 22 Aug - 23 Aug 22 Aug - 25 Aug Completed
Deployment
  • Testing
Qian Hwee 24 Aug 25 Aug Completed
  • Document Full Test Cases
Zou Mei 24 Aug 26 Aug Completed
Buffer 25 Aug - 26 Aug 2 Buffer day used
Acceptance - 15 Aug
Preparation of Acceptance Presentation
  • Update of Wiki
Zou Mei, Jasmine, Shoe 31 July - 14 Aug 31 July - 14 Aug Completed
  • Acceptance Slides
Shoe, Zou Mei 1 Aug - 14 Aug 1 Aug - 14 Aug Completed
Iteration 4 27 Aug - 12 Sept 27 Aug - 15 Sept
Documentation
  • Update Use Case
Zou Mei 27 Aug 27 Aug Completed
  • Update Domain Diagram
Shoe 27 Aug 27 Aug Completed
  • Create Test Cases for Spree Management
Jasmine 27 Aug 27 Aug Completed
Development
Spree Management Ryan 80% Completed
  • Create Spree
28 Aug - 8 Sept 28 Aug - 9 Sept
  • Remove Spree
28 Aug - 8 Sept 28 Aug - 9 Sept
  • Close Spree
28 Aug - 8 Sept 28 Aug - 9 Sept
  • Filter Ongoing Sprees
28 Aug - 8 Sept 28 Aug - 9 Sept
  • Spree Status
28 Aug - 8 Sept 28 Aug - 9 Sept
  • Notification center (Payment Verification)
28 Aug - 8 Sept 28 Aug - 9 Sept
UI Portal Design Qian Hwee Completed
  • Main Page
28 Aug - 8 Sept 28 Aug - 10 Sept
  • UI Implementation
28 Aug - 8 Sept 28 Aug - 10 Sept

UI Plugin

28 Aug - 8 Sept 28 Aug - 10 Sept
Unit Testing
  • Testing
Zou Mei 9 Sept 11 Sept Completed
  • Document Test Cases
Qian Hwee 9 Sept 11 Sept Completed
Integration
  • Integration
Ryan 10 Sept - 11 Sept 13 Sept Completed
  • Debugging
Zhen Guang 10 Sept - 11 Sept 13 Sept Completed
Deployment
  • Testing
Shoe 12 Sept 15 Sept Completed
  • Document Full Test Cases
Jasmine 12 Sept 15 Sept Completed
Buffer 13 Sept - 15 Sept 3 Buffer day used
1st User Testing - 14 Sept @ 12.30pm
Documentation for 1st User Testing (Participants)
  • Gathering of Users for User Test
Jasmine, Zhen Guang 10 Sept - 14 Sept 10 Sept - 14 Sept Completed
  • Preparing for User Test Survey
Shoe, Jasmine 10 Sept - 14 Sept 10 Sept - 14 Sept Completed
  • Preparing for User Test Scenario
Zou Mei 10 Sept - 14 Sept 10 Sept - 14 Sept Completed
  • Collating and gathering Feedback from User Test
Shoe, Zou Mei, Jasmine 15 Sept - 16 Sept 15 Sept - 16 Sept Completed
Iteration 5 16 Sept - 28 Sept 16 Sept - 6 Oct
Documentation
  • Update Use Case
Qian Hwee 16 Sept 16 Sept Completed
  • Update Domain Diagram
Jasmine 16 Sept 16 Sept Completed
Development
Improvement from User Testing 1 Completed
  • UI Improvement
Qian Hwee 17 Sept - 23 Sept 17 Sept - 2 Oct Completed
  • Tag and Bag Improvement
Zhen Guang 17 Sept - 23 Sept 17 Sept - 23 Sept Completed
  • Portal Improvement
Ryan, Qian Hwee 17 Sept - 23 Sept 17 Sept - 2 Oct Completed
  • Spree Management Improvement
Zhen Guang 17 Sept - 23 Sept 17 Sept - 2 Oct Completed
  • User Management Improvement
Ryan 17 Sept - 23 Sept 17 Sept - 2 Oct Completed
Spree Management Completed
  • Back-End Logic component
Ryan 17 Sept - 23 Sept 3 Oct Newly Added
Unit Testing
  • Testing
Shoe 24 Sept 3 Oct Completed
  • Document Test Cases
Zou Mei 24 Sept 3 Oct Completed
Integration
  • Integration
Zhen Guang 25 Sept - 27 Sept 4 Oct - 5 Oct Completed
  • Debugging
Ryan 25 Sept - 27 Sept 4 Oct - 5 Oct Completed
Deployment
  • Testing
Jasmine 28 Sept 6 Oct Completed
  • Document Full Test Cases
Shoe 28 Sept 6 Oct Completed
Buffer 29 Sept - 30 Sept Buffer days were used
2nd User Testing - 7 Oct @ 12.30pm
Documentation for 2nd User Testing (Organiser)
  • Gathering of Users for User Test
Jasmine, Zhen Guang 21 Sept - 27 Sept 21 Sept - 27 Sept Completed
  • Preparing for User Test Survey
Shoe, Jasmine 21 Sept - 27 Sept 21 Sept - 27 Sept Completed
  • Preparing for User Test Scenario
Zou Mei 21 Sept - 27 Sept 21 Sept - 27 Sept Completed
  • Collating and gathering Feedback from User Test
Shoe, Zou Mei, Jasmine 28 Sept - 5 Oct 28 Sept - 7 Oct Completed
Mid Term - 9 Oct @ 2pm
Preparation of Mid Term Presentation
  • Update of Wiki
Zou Mei, Jasmine, Shoe 1 Oct - 7 Oct 1 Oct - 7 Oct Completed
  • Mid Term Slides
Shoe, Zou Mei 1 Oct - 7 Oct 1 Oct - 7 Oct Completed
Iteration 6 15 Oct - 2 Nov 15 Oct - 3 Nov
Documentation
  • Update Use Case
Zou Mei 15 Oct 15 Oct Completed
  • Update Domain Diagram
Shoe 15 Oct 15 Oct Completed
  • Create Test Cases for Credit Management
Jasmine 15 Oct 15 Oct Completed
Development
Credit Management Ryan 80% Completed
  • View Credit Balance
16 Oct - 29 Oct 16 Oct - 30 Oct Completing in Iteration 7
  • Add Credit
16 Oct - 29 Oct 16 Oct - 30 Oct Completing in Iteration 7
  • Top Up Credit
16 Oct - 29 Oct 16 Oct - 30 Oct
  • Refund Credit
16 Oct - 29 Oct 16 Oct - 30 Oct
User Management Zhen Guang Functionality Dropped
  • Ratings
16 Oct - 29 Oct Not Completed
Spree Management 100% Completed
  • Notification Center (Payment Verification)
Zhen Guang 16 Oct - 29 Oct 16 Oct - 30 Oct
  • Back-End Logic Component
Ryan 16 Oct - 29 Oct 16 Oct - 30 Oct
Unit Testing
  • Testing
Zou Mei 30 Oct 31 Oct Completed
  • Document Test Cases
Qian Hwee 30 Oct 31 Oct Completed
Integration
  • Integration
Ryan 31 Oct - 1 Nov 2 Nov Completed
  • Debugging
Zhen Guang 31 Oct - 1 Nov 2 Nov Completed
Deployment
  • Testing
Shoe 2 Nov 3 Nov Completed
  • Document Full Test Cases
Jasmine 2 Nov 3 Nov Completed
Buffer 2 Nov - 4 Nov 1 Buffer day used
Iteration 7 5 Nov - 16 Nov 5 Nov - 17 Nov
Documentation
  • Update Use Case
Qian Hwee 5 Nov 5 Nov Completed
  • Update Domain Diagram
Jasmine 5 Nov 5 Nov Completed
  • Create Test Cases for Social Integration
Zou Mei 5 Nov 5 Nov Completed
Development
Social Integration Zhen Guang, Qian Hwee 90% Completed
  • Login Through Facebook
6 Nov - 12 Nov 6 Nov - 8 Nov
  • Sharing of Favorites through Facebook
6 Nov - 12 Nov 6 Nov - 12 Nov
  • Embedding Widgets
6 Nov - 12 Nov Not Completed Shift to Iteration 8
Credit Management Ryan Completed
  • View Credit Balance (For Participants)
6 Nov - 12 Nov 6 Nov - 13 Nov
  • Add Credit (For Participants)
6 Nov - 12 Nov 6 Nov - 13 Nov
Unit Testing
  • Testing
Shoe 13 Nov 14 Nov Completed
  • Document Test Cases
Zou Mei 13 Nov 14 Nov Completed
Integration
  • Integration
Zhen Guang 14 Nov - 15 Nov 15 Nov - 16 Nov Completed
  • Debugging
Ryan 14 Nov - 15 Nov 15 Nov - 16 Nov Completed
Deployment
  • Testing
Jasmine 16 Nov 17 Nov Completed
  • Document Full Test Cases
Shoe 16 Nov 17 Nov Completed
Buffer 17 Nov 1 Buffer day used
3rd User Testing - 16 Nov @ 12.30pm
Documentation for 3rd User Testing (Organiser & Participants) - 16 Nov
  • Gathering of Users for User Test
Jasmine, Zhen Guang 12 Nov - 15 Nov 12 Nov - 15 Nov Completed
  • Preparing for User Test Survey
Shoe, Jasmine 12 Nov - 15 Nov 12 Nov - 15 Nov Completed
  • Preparing for User Test Scenario
Zou Mei 12 Nov - 15 Nov 12 Nov - 15 Nov Completed
  • Collating and gathering Feedback from User Test
Shoe, Zou Mei, Jasmine 19 Nov - 21 Nov 19 Nov - 21 Nov Completed
Iteration 8 18 Nov - 29 Nov 18 Nov - 29 Nov
Documentation
  • Update Use Case
Shoe 18 Nov 18 Nov Completed
  • Update Domain Diagram
Zou Mei 18 Nov 18 Nov Completed
  • Create Test Cases for Backend Admin Functions
Jasmine 18 Nov 18 Nov Completed
Development
Backend Admin Functions
  • Audit Trial (Log)
Ryan 19 Nov - 25 Nov 19 Nov - 23 Nov Completed
Tag and Bag Framework (Plugin)
  • Error Reporting
Zhen Guang 19 Nov - 25 Nov 19 Nov - 19 Nov Completed
Social Integration
  • Embedding Widgets
Qian Hwee 19 Nov - 25 Nov 19 Nov - 25 Nov Completed
Backend
  • Ability Functions
Ryan 19 Nov - 25 Nov 23 Nov - 25 Nov Completed
Unit Testing
  • Testing
Jasmine 26 Nov 26 Nov Completed
  • Document Test Cases
Shoe 26 Nov 26 Nov Completed
Integration
  • Integration
Zhen Guang 27 Nov - 28 Nov 27 Nov - 28 Nov Completed
  • Debugging
Ryan 27 Nov - 28 Nov 27 Nov - 28 Nov Completed
Deployment
  • Testing
Qian Hwee 29 Nov 29 Nov Completed
  • Document Full Test Cases
Zou Mei 29 Nov 29 Nov Completed
Buffer 30 Nov - 5 Dec
Final Presentation - 5 Dec @ 6.30pm
Preparation of Final Presentation
  • Update of Wiki
Zou Mei, Jasmine, Shoe 29 Nov - 4 Dec 29 Nov - 4 Dec Completed
  • Final Presentation Slides
Shoe, Zou Mei 29 Nov - 4 Dec 29 Nov - 4 Dec Completed
Iteration 9 10 Dec - 21 Dec
Documentation
  • Update Use Case
Zou Mei 10 Dec
  • Update Domain Diagram
Shoe 10 Dec
  • Create Test Cases for Spree Management
Jasmine 10 Dec
Development
Admin Control Management Ryan 11 Dec - 17 Dec
  • Set Roles
11 Dec - 17 Dec
  • Monitor Audit Log
11 Dec - 17 Dec
  • Credit of Funds
11 Dec - 17 Dec
  • Approve Organiser
11 Dec - 17 Dec
  • Resolve Conflict
11 Dec - 17 Dec
Unit Testing
  • Testing
Zou Mei 18 Dec
  • Document Test Cases
Qian Hwee 18 Dec
Integration
  • Integration
Ryan 19 - 20 Dec
  • Debugging
Zhen Guang 19 - 20 Dec
Deployment
  • Testing
Shoe 21 Dec
  • Document Full Test Cases
Jasmine 21 Dec
Buffer 22 Dec - 24 Dec
Iteration 10 31 Dec - 20 Jan
Documentation
  • Update Use Case
Qian Hwee 31 Dec
  • Update Domain Diagram
Jasmine 31 Dec
  • Create Test Cases for Spree Management
Zou Mei 31 Dec
Development
Offline Product Management Zheng Guan, Ryan, Qian Hwee
  • Add Offline Products
1 Jan - 15 Jan
  • Check Out Offline Products
1 Jan - 15 Jan
  • Managed Offline Product Verification
1 Jan - 15 Jan
Unit Testing
  • Testing
Jasmine 16 Jan
  • Document Test Cases
Shoe 16 Jan
Integration
  • Integration
Zhen Guang 17 Jan - 19 Jan
  • Debugging
Ryan 17 Jan - 19 Jan
Deployment
  • Testing
Qian Hwee 20 Jan
  • Document Full Test Cases
Zou Mei 20 Jan
Buffer 21 Jan - 31 Jan
4rd User Testing - 31 Jan
Documentation for 4th User Testing (Organiser & Participants)
  • Gathering of Users for User Test
Jasmine, Zhen Guang 21 Jan - 30 Jan
  • Preparing for User Test Survey
Shoe, Jasmine 21 Jan - 30 Jan
  • Preparing for User Test Scenario
Zou Mei 21 Jan - 30 Jan
  • Collating and gathering Feedback from User Test
Shoe, Zou Mei, Jasmine 31 Jan - 7 Feb