Schedule

View our actual Schedule

Schedule Summary

STEEPScheduleSummary.png

Metrics

Bug Metric

Objective : To ensure an error-free application

Schedule Metric

Objective : To improve schedule estimation accuracy

Our Schedule Metric is calculated at the end of every iteration.

Schedule Metric

Risks

Risk Assessment

STEEPRiskAssessment.png

Risks & Mitigation Strategy

S/No Type of Risk Risk Statement Impact Level Likelihood Risk Assessment Mitigation Strategy
1 Resource Risk Insufficient android mobile phones during development and User Testing High Low High A
  • Plan UAT early and inform sponsors the number of mobile phones required
  • Sponsors would be providing the mobile phones
  • Borrow from friends
2 Technical Risk Working with new technology and tools Medium High A
  • Arrange group sharing/learning sessions to improve knowledge
  • Allocate sufficient time to familiarize with new technology and tools
3 Resource Risk Insufficient time for User Testing with SMU students Medium Medium B
  • Plan to complete all functionalities early to prepare for User Testing

Tools

- Microsoft Visual Studio
- Microsoft SQL Server
- Android SDK
- Eclipse Helios
- Adobe Photoshop

- Google Play
- Microsoft Azure

- Dropbox
- Google Docs
- IS480 Wikipedia
- Email


- Microsoft Project
- Microsoft Visio

Minutes