Revision as of 17:35, 9 October 2012
Home |
Project Progress Summary
Mid-Term Presentation Slides: Pro-cept - Mid-Term Presentation
Website Link: http://www.proclab.com/Pro-Cept/login2.jsp
Overview
As of 7 Oct 2012, Pro-cept has completed 7 of the assigned functionalities, after 10 iterations of the project.
During these 5 months, our team has achieved several key accomplishments since the project progress on 21 May 2012:
- Exposure to 3rd party sources in the process of developing our project
- Use of Google Doc List API in the process of developing the Google Doc Integration
- Hosting of 2 Usability Tests and and using the feedback to improve our website to better suits users
Pro-cept is currently on track according to our schedule and hence we are confident of completing the project within the Schedule.
Project Highlights
Event | Highlights/Issue Description |
1 |
Delay in completing Google Doc Integration in Iteration 7
|
2 |
Lack of Project Requirements
|
Project Management
Project Status
Feature | Status | Confident Level (0 - 1) | Person In-Charge |
Task List Calendar | 100% developed and deployed |
1 | Wee Long & Kelvin Tan |
Newsfeed | 100% developed and deployed |
1 | Christie |
Project Group | 100% developed and deployed |
1 | Kelvin Tan |
Google Doc Integration | 80% developed and deployed |
1 | Christie |
Chronoline (Timeline) | 100% developed and deployed |
1 | Wee Long |
Minute Taker | 80% developed and deployed |
1 | Christie |
Document View | 100% developed and deployed |
1 | Wee Long |
Chat | Not Started |
1 | Kelvin Tan |
Filtering | Not Started |
1 | Wen Xiong |
Project Schedule (Planned VS. Actual)
Functions | Task | Planned Schedule | Actual Schedule | Comment | ||
Start Date | End Date | Start Date | End Date | |||
Task List Calendar | Create Task Function | 19 Jun 2012 | 20 Jun 2012 | 19 Jun 2012 | 20 Jun 2012 | |
Retrieve Task Function | 21 Jun 2012 | 22 Jun 2012 | 21 Jun 2012 | 22 Jun 2012 | ||
Update Task Function | 23 Jun 2012 | 23 Jun 2012 | 23 Jun 2012 | 23 Jun 2012 | ||
Delete Task Function | 24 Jun 2012 | 24 Jun 2012 | 24 Jun 2012 | 24 Jun 2012 | ||
Create Calendar Function | 25 Jun 2012 | 25 Jun 2012 | 25 Jun 2012 | 25 Jun 2012 | ||
Retrieve Calendar Function | 26 Jun 2012 | 26 Jun 2012 | 26 Jun 2012 | 26 Jun 2012 | ||
Update Calendar Function | 27 Jun 2012 | 27 Jun 2012 | 27 Jun 2012 | 27 Jun 2012 | ||
Delete Calendar Function | 28 Jun 2012 | 28 Jun 2012 | 28 Jun 2012 | 28 Jun 2012 | ||
Newsfeed | Create Newsfeed Function (All, Personal, Group) | 3 Jul 2012 | 4 Jul 2012 | 3 Jul 2012 | 4 Jul 2012 | |
Retrieve Newsfeed Function | 5 Jul 2012 | 6 Jul 2012 | 5 Jul 2012 | 6 Jul 2012 | ||
Update Newsfeed Function | 7 Jul 2012 | 8 Jul 2012 | 7 Jul 2012 | 8 Jul 2012 | ||
Delete Newsfeed Function | 9 Jul 2012 | 9 Jul 2012 | 9 Jul 2012 | 9 Jul 2012 | ||
Project Group | Create Form | 17 Jul 2012 | 19 Jul 2012 | 17 Jul 2012 | 19 Jul 2012 | |
Check User Function | 20 Jul 2012 | 21 Jul 2012 | 20 Jul 2012 | 21 Jul 2012 | ||
Insert data to Database | 22 Jul 2012 | 23 Jul 2012 | 22 Jul 2012 | 23 Jul 2012 | ||
Google Doc Integration | Code Oauth | 31 Jul 2012 | 3 Aug 2012 | 31 Jul 2012 | 3 Aug 2012 | |
Code Logging In | 4 Aug 2012 | 6 Aug 2012 | 4 Aug 2012 | 6 Aug 2012 | ||
Code Refresh of Access | 7 Aug 2012 | 9 Aug 2012 | 7 Aug 2012 | 9 Aug 2012 | ||
Retrieve Files (Real-Time) | 13 Aug 2012 | 14 Aug 2012 | 13 Aug 2012 | 14 Aug 2012 | ||
Update Files | 15 Aug 2012 | 16 Aug 2012 | 15 Aug 2012 | 16 Aug 2012 | ||
Create Files | 17 Aug 2012 | 18 Aug 2012 | 17 Aug2012 | 25 Aug 2012 | Unable to complete this two tasks on time, thus we have to spilled over these two tasks to iteration 8 where we will be doing Chronoline (Timeline) concurrently. | |
Delete Files | 19 Aug 2012 | 20 Aug 2012 | 26 Aug 2012 | 3 Sep 2012 | ||
Chronoline (Timeline) | Create Milestones/Deadline | 28 Aug 2012 | 29 Aug 2012 | 28 Aug 2012 | 29 Aug 2012 | |
Retrieve Milestones/Deadline | 30 Aug 2012 | 31 Aug 2012 | 30 Aug 2012 | 31 Aug 2012 | ||
Update Milestones/Deadline | 1 Sep 2012 | 2 Sep 2012 | 1 Sep 2012 | 2 Sep 2012 | ||
Delete Milestones/Deadline | 3 Sep 2012 | 3 Sep 2012 | 3 Sep 2012 | 3 Sep 2012 | ||
Minute Taker | Create Form List (Adding of Minute) | 11 Sep 2012 | 12 Sep 2012 | 11 Sep 2012 | 12 Sep 2012 | |
Retrieve User List | 13 Sep 2012 | 14 Sep 2012 | 13 Sep 2012 | 14 Sep 2012 | ||
Update Minute to DOC Format | 15 Sep 2012 | 16 Sep 2012 | 15 Sep 2012 | 16 Sep 2012 | ||
Delete Minute | 17 Sep 2012 | 17 Sep 2012 | 17 Sep 2012 | 17 Sep 2012 | ||
Document View | Code Opening GDOC link in I-Frame | 25 Sep 2012 | 28 Sep 2012 | 25 Sep 2012 | 28 Sep 2012 | |
Code Opening subsequent GDOC link in I-Frame | 29 Sep 2012 | 1 Oct 2012 | 29 Sep 2012 | 1 Oct 2012 |
Project Metrics
Schedule Metric
The diagram below shows the charts of the 10 iterations we have completed.
PUT DIAGRAM HERE!
Links:
Bug Metric
Number of Bugs FoundThere was a pike in the number of bugs found in Iteration 9. This is because of the conducting of User Testing 1 in iteration 9.
|
---|
Bug Metric Severity ChartThis Bug Metric Severity Chart shows the corresponding severity score with the number of bugs found.
|
---|
Links:
Project Risks
Risk | Risk Description | Impact | Impact Level (Low/Med/High) | Likelihood Level (Low/Med/High) | Mitigation Strategy | Status |
Project Management Risk | ||||||
1 | Self-initiated project does not provide us with the required set of requirement for our project scope | Scope of Project Scope | High | High | To conduct Usability Testing to gather user's feedbacks and suggestion on what they want for the project. | Mitigation strategy in force |
Acceptance Risk | ||||||
2 | End user's unwillingness to switch to our platform for managing of their projects | Project will be useless | High | High | The need to create a user-intuitive platform for ease of use to attract end users | Mitigation strategy in force |
Technical Complexity
Technical complexity are listed in the order of highest complexity:
S/No | Description |
1. Customization of Task List Calendar with 3rd Party (Full Calendar) |
What the feature is about?
|
2. Uploading of Google Docs |
What the feature is about?
|
3. Complexity of integrating with Google Doc Integration and Minute Taker together |
What the feature is about?
|
Quality of Product
Intermediate Deliverables
Stage | Specification | Modules |
Project Management | Minutes | |
Metrics | ||
Proposal/Powerpoint Document | ||
Requirements | User Interface - Storyboard | |
Website (Live) | ||
Analysis | Use Case Diagram | |
Sequence Diagram | ||
Design | ER Diagram | |
Logical Diagram | ||
Class Diagram | ||
Deployment Diagram | ||
Architecture Diagram | ||
Testing | Pro-cept Test Case | |
User Testing Documents | ||
User Testing - Criteria List |
Deployment
- Staging & Development Environment: Deployed on VMWare at IS480 Server
- Database: MySQL
- Web Services: Google RESTFUL webservices
- Web Links: View our Deployment Diagram Here!
Testing
Reflection