Time Management

Risk Management

Quality Management

Meeting Minutes

Submission Materials

Risk Metric

Risk Metric OHW.png

No. Risk Statement Type of Risk Likelihood (H/M/L) Impact Mitigation Strategy / Contingency Plan
1 Difficulty in implementing customizable template for job seekers to drag and drop content into the template Technical Low Low Team already tried Jquery Drag & Drop feature & implemented it under Resume function. (Not a huge risk to the team for late implementation)
2 Due to similar applications launch in the market, there might be unexpected change of requirements by sponsor External Medium Low Fortnightly update/meeting with sponsor – Kris Kong & Wong Cheok Lup
3 Team is unfamiliar with the new framework - Play! Framework Technical Low Moderate Set aside more time to code.
4 Deployment. Deploying to client server may take a long time and errors may appear. Technical Medium High Always deploy in advance (1 week before) & test run the application.
5 Schedule. Team members are busy with school work. Internal Low Moderate Plan ahead and make sure that all team members are comfortable with the work load and free to meet on the dates scheduled. Team members to encourage each other and make extra effort to accommodate to each other and keep in pace with the schedule. Set weekly compulsory meeting dates.