Difference between revisions of "IS480 Team wiki: 2012T1 One-hit Wonder Project Management Risk"
Jump to navigation
Jump to search
(12 intermediate revisions by 2 users not shown) | |||
Line 57: | Line 57: | ||
|} | |} | ||
− | [[Image:Risk Metric OHW.png| | + | [[Image:Risk Metric OHW.png|500px]] |
<br> | <br> | ||
{| class="wikitable" cellpadding="15" | {| class="wikitable" cellpadding="15" | ||
− | |- | + | |- style= "background: #BDECB6; text-align: center; font-weight: bold; font-size:16px; " |
− | + | | No. | |
− | + | | Risk Statement | |
− | + | | Type of Risk | |
− | + | | Likelihood (H/M/L) | |
− | | | + | | Impact |
− | | style= "background: # | + | | Mitigation Strategy / Contingency Plan |
− | + | |- style= "background: #E5F8E2; " | |
| 1 | | 1 | ||
| Difficulty in implementing customizable template for job seekers to drag and drop content into the template | | Difficulty in implementing customizable template for job seekers to drag and drop content into the template | ||
Line 75: | Line 75: | ||
| Low | | Low | ||
| Team already tried Jquery Drag & Drop feature & implemented it under Resume function. (Not a huge risk to the team for late implementation) | | Team already tried Jquery Drag & Drop feature & implemented it under Resume function. (Not a huge risk to the team for late implementation) | ||
− | |- | + | |- style= "background: #E5F8E2; " |
| 2 | | 2 | ||
| Due to similar applications launch in the market, there might be unexpected change of requirements by sponsor | | Due to similar applications launch in the market, there might be unexpected change of requirements by sponsor | ||
Line 82: | Line 82: | ||
| Low | | Low | ||
| Fortnightly update/meeting with sponsor – Kris Kong & Wong Cheok Lup | | Fortnightly update/meeting with sponsor – Kris Kong & Wong Cheok Lup | ||
− | |- | + | |- style= "background: #E5F8E2; " |
| 3 | | 3 | ||
| Team is unfamiliar with the new framework - Play! Framework | | Team is unfamiliar with the new framework - Play! Framework | ||
| Technical | | Technical | ||
| Low | | Low | ||
− | | | + | | Medium |
| Set aside more time to code. | | Set aside more time to code. | ||
− | |- | + | |- style= "background: #FFA8A8; " |
| 4 | | 4 | ||
| Deployment. Deploying to client server may take a long time and errors may appear. | | Deployment. Deploying to client server may take a long time and errors may appear. | ||
Line 96: | Line 96: | ||
| High | | High | ||
| Always deploy in advance (1 week before) & test run the application. | | Always deploy in advance (1 week before) & test run the application. | ||
− | |- | + | |- style= "background: #E5F8E2; " |
| 5 | | 5 | ||
| Schedule. Team members are busy with school work. | | Schedule. Team members are busy with school work. | ||
| Internal | | Internal | ||
| Low | | Low | ||
− | | | + | | Medium |
| Plan ahead and make sure that all team members are comfortable with the work load and free to meet on the dates scheduled. Team members to encourage each other and make extra effort to accommodate to each other and keep in pace with the schedule. Set weekly compulsory meeting dates. | | Plan ahead and make sure that all team members are comfortable with the work load and free to meet on the dates scheduled. Team members to encourage each other and make extra effort to accommodate to each other and keep in pace with the schedule. Set weekly compulsory meeting dates. | ||
+ | |- | ||
|} | |} | ||
+ | |||
+ | Click here to view our [[IS480 Team wiki: 2012T1 One-hit Wonder MT Project Metrics Risk | Updated Risks]] |
Latest revision as of 13:33, 8 October 2012
Risk Metric |
No. | Risk Statement | Type of Risk | Likelihood (H/M/L) | Impact | Mitigation Strategy / Contingency Plan |
1 | Difficulty in implementing customizable template for job seekers to drag and drop content into the template | Technical | Low | Low | Team already tried Jquery Drag & Drop feature & implemented it under Resume function. (Not a huge risk to the team for late implementation) |
2 | Due to similar applications launch in the market, there might be unexpected change of requirements by sponsor | External | Medium | Low | Fortnightly update/meeting with sponsor – Kris Kong & Wong Cheok Lup |
3 | Team is unfamiliar with the new framework - Play! Framework | Technical | Low | Medium | Set aside more time to code. |
4 | Deployment. Deploying to client server may take a long time and errors may appear. | Technical | Medium | High | Always deploy in advance (1 week before) & test run the application. |
5 | Schedule. Team members are busy with school work. | Internal | Low | Medium | Plan ahead and make sure that all team members are comfortable with the work load and free to meet on the dates scheduled. Team members to encourage each other and make extra effort to accommodate to each other and keep in pace with the schedule. Set weekly compulsory meeting dates. |
Click here to view our Updated Risks