Task Name | In-Charge | Planned Start | Planned End | Planned Duration (days) | Actual Start | Actual End | Actual Duration (days) | Status | Schedule Index |
---|---|---|---|---|---|---|---|---|---|
Iteration 0 - Requirements Gathering | |||||||||
Understanding client's requirements | Vivian | 14/5/12 | 18/5/12 | 5 | 14/5/12 | 20/5/12 | 5 | Completed | 1 |
Technology Research Phrase | |||||||||
Research on various framework (Spring, Play! Etc) | Jia Yi | 14/5/12 | 29/5/12 | 12 | 14/5/12 | 30/5/12 | 13 | Completed | 1.08 |
Project Management Plan | |||||||||
Define team's roles and responsibilities | Vivian | 31/5/12 | 1/6/12 | 2 | 31/5/12 | 1/6/12 | 2 | Completed | 1 |
Define project schedule & milestone | Vivian | 31/5/12 | 5/6/12 | 4 | 31/5/12 | 6/6/12 | 5 | Completed | 1.25 |
Identify risk and issues | Vivian | 31/5/12 | 1/6/12 | 2 | 31/5/12 | 1/6/12 | 2 | Completed | 1 |
Determine project scope and methodology | Vivian | 30/6/12 | 12/6/12 | 10 | 30/6/12 | 12/6/12 | 10 | Completed | 1 |
Define Project Methodology | |||||||||
Identify framework | Jia Yi | 31/5/12 | 31/5/12 | 1 | 31/5/12 | 31/5/12 | 1 | Completed | 1 |
Identify resources and reference | Jia Yi | 31/5/12 | 31/5/12 | 1 | 31/5/12 | 31/5/12 | 1 | Completed | 1 |
Design Phase | |||||||||
Design team's Logo | Krisabelle | 4/6/12 | 6/6/12 | 3 | 4/6/12 | 7/6/12 | 4 | Completed | 1.33 |
User interface of Wiki's page | Krisabelle | 11/6/12 | 15/6/12 | 5 | 8/6/12 | 15/6/12 | 6 | Completed | 1.2 |
Documentation | |||||||||
Create use-case diagrams & descriptions | Shuya | 11/6/12 | 13/6/12 | 3 | 11/6/12 | 13/6/12 | 3 | Completed | 1 |
Final editing of project proposal | Vivian | 13/6/12 | 19/6/12 | 5 | 13/6/12 | 18/6/12 | 4 | Completed | 0.8 |
Proposal Submission | |||||||||
Iteration 1 - Login & Manage User Account | |||||||||
Project Management Plan | |||||||||
Design metrics (Bugs & Schedule) | Vivian | 21/6/12 | 26/6/12 | 4 | 21/6/12 | 25/6/12 | 3 | Completed | 0.75 |
Business Modelling | |||||||||
Create sequence diagrams - Login & Manage Account | Shuya | 21/6/12 | 25/6/12 | 3 | 21/6/12 | 25/6/12 | 3 | Completed | 1 |
Develop storyboard - Login & Signup page | Krisabelle | 21/6/12 | 26/6/12 | 4 | 21/6/12 | 26/6/12 | 4 | Completed | 1 |