1
|
Heuristic Evaluation
|
Major changes in user interface after Heuristic Evaluation: User interface was redesigned to standardized all buttons and layout.
|
2
|
User Testing 1
|
Major changes made to data validation: Changed as many server-side validations to client-side validation.
|
3
|
Project Management
|
Implementation of changes from User Test 1 in Iteration 5 took longer than we expected: Due to major changes made to both the back-end and front-end codes, our team completed all amendments 4 days after the scheduled deadline.
|
4
|
Drop Functionality
|
LinkedIn Login and data extraction was removed in Iteration 5: Despite attempting to implement this function in both Iteration 1 and 5, due to complexity of the function, we were unable to deliver successfully, so our team negotiated with our client/supervisor and came to the conclusion to drop the function.
|
5
|
Change in Functionalities
|
Tagging and filtering function in Iteration 5 was changed to basic ‘Search’ function which will be implemented after mid-terms: Taking the time constraint into consideration, after the requirement gathering session with our client in Iteration 5, the change in functionality was confirmed.
|