User Testing 2

Our User Testing 2 (UT2) will take place on 2 November.

Objectives

  • Verify if users can react to AlterSense without prompting
  • Test the intuitiveness of our user interface (photo taking) and hand gestures
  • Gather user opinion on AlterSense feasibility in a mall setting
  • Test the accuracy of gender recognition in a mall setting

Location

  • Plaza Singapura (tentatively)

Testers

  • General public

Quantitative metric

  • Time taken for user to raise his/her right hand to take a photo
  • No. of failed detections of raising of right hand
  • Response time for user to scan the Microsoft tag
  • No. of failed attempts to scan the Microsoft tag

Execution Flow

1. Let user use AlterSense by himself/herself
2. Observe user if he/she has any difficulties responding to AlterSense
3. Measure the time taken for user to raise his/her right hand and to scan the Microsoft tag
4. Let user complete a survey form