Difference between revisions of "IS480 Team wiki: 2012T1 M.O.O.T/Project Management/Risk Management"
Jump to navigation
Jump to search
Line 69: | Line 69: | ||
|- | |- | ||
| 2 | | 2 | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
| Accuracy of gender recognition | | Accuracy of gender recognition | ||
| | | | ||
Line 90: | Line 78: | ||
| | | | ||
|- | |- | ||
− | | | + | | 3 |
| No suitable gestures library that we can use | | No suitable gestures library that we can use | ||
| | | | ||
Line 101: | Line 89: | ||
| | | | ||
|- | |- | ||
− | | | + | | 4 |
| Self-written motion gestures may be inaccurate/inconsistent/too difficult to perform. | | Self-written motion gestures may be inaccurate/inconsistent/too difficult to perform. | ||
| | | | ||
Line 113: | Line 101: | ||
| | | | ||
|- | |- | ||
− | | | + | | 5 |
| Team is unfamiliar with working with new technology & tools | | Team is unfamiliar with working with new technology & tools | ||
| | | | ||
Line 127: | Line 115: | ||
| style="background: #C8BBBE;" colspan="7" | Scope Risk | | style="background: #C8BBBE;" colspan="7" | Scope Risk | ||
|- | |- | ||
− | | | + | | 6 |
| Sponsor changes his requirements frequently | | Sponsor changes his requirements frequently | ||
| | | | ||
Line 140: | Line 128: | ||
| | | | ||
|- | |- | ||
− | | | + | | 7 |
| Team overpromising new features | | Team overpromising new features | ||
| | | | ||
Line 153: | Line 141: | ||
|- | |- | ||
− | | | + | | 8 |
| There is a critical bug that affects the core functionalities | | There is a critical bug that affects the core functionalities | ||
| | | | ||
Line 167: | Line 155: | ||
|- | |- | ||
− | | | + | | 9 |
| Team members have other commitments and different priorities | | Team members have other commitments and different priorities | ||
| | | |
Revision as of 16:46, 17 September 2012
Project Schedule | Methodology | Metrics | Risk Management | Minutes Repository |
Risk Management
S/N | Risk Statement | Impact | Likelihood | Impact Level | Mitigation Strategy | Status |
Technology & Learning Risk | ||||||
1 | No library available for gender recognition |
|
High | High |
|
|
2 | Accuracy of gender recognition |
|
High | High |
|
|
3 | No suitable gestures library that we can use |
|
High | High |
|
|
4 | Self-written motion gestures may be inaccurate/inconsistent/too difficult to perform. |
|
High | High |
|
|
5 | Team is unfamiliar with working with new technology & tools |
|
High | High |
|
|
Scope Risk | ||||||
6 | Sponsor changes his requirements frequently |
|
Medium | Medium |
|
|
7 | Team overpromising new features |
|
Medium | Medium |
|
|
Development Risk | ||||||
8 | There is a critical bug that affects the core functionalities |
|
High | High |
|
|
Schedule Risk | ||||||
9 | Team members have other commitments and different priorities |
|
Medium | High |
|