Difference between revisions of "IS480 Team wiki: 2012T1 M.O.O.T/Project Management/Metrics"
Jump to navigation
Jump to search
Line 30: | Line 30: | ||
{| style="background-color:#ffffff; border-bottom: 8px solid #9400D3; color:#000000" width="100%" cellspacing="0" cellpadding="6" valign="top" border="0" | | {| style="background-color:#ffffff; border-bottom: 8px solid #9400D3; color:#000000" width="100%" cellspacing="0" cellpadding="6" valign="top" border="0" | | ||
− | | style="font-size:90%; text-align:center; color:#000000" width="10%" |[[ | + | | style="font-size:90%; text-align:center; color:#000000" width="10%" |[[ IS48 0Team wiki: 2012T1 M.O.O.T/Project Management|<font color="#000000">Project Schedule</font>]] |
− | | style="font-size:90%; text-align:center; color:#000000" width="10%" |[[ | + | | style="font-size:90%; text-align:center; color:#000000" width="10%" |[[ IS480 Team wiki: 2012T1 M.O.O.T/Project Management/Methodology|<font color="#000000">Methodology</font>]] |
| style="font-size:90%; text-align:center; background-color:#9400D3; color:#000000" width="10%" |[[ IS480 Team wiki: 2012T1 M.O.O.T/Project Management/Metrics|<font color="#ffffff">Metrics</font>]] | | style="font-size:90%; text-align:center; background-color:#9400D3; color:#000000" width="10%" |[[ IS480 Team wiki: 2012T1 M.O.O.T/Project Management/Metrics|<font color="#ffffff">Metrics</font>]] | ||
Line 62: | Line 62: | ||
<br> | <br> | ||
− | [[Image: | + | [[Image:MOOT_schedule_metric.png|center|740px]] |
<center> | <center> |
Revision as of 18:25, 22 September 2012
Project Schedule | Methodology | Metrics | Risk Management | Minutes Repository |
Bug Metrics
Bug metrics are used to ensure the quality of the application by keeping track of the number of bugs that occur during development.
Bug metrics document
Velocity Metrics
Velocity metrics ensure that our project tasks are completed within the schedule timeframe so that the project deadline can be met. The score is retrieved from Pivotal Tracker.
Iteration-Velocity Progress | |||||||
Iteration No. |
Start Date |
End Date |
No. of Days |
Points | Baseline Velocity | Score (Pts - Velocity) |
Remarks |
1 | 17/08/2012 | 01/09/2012 | 14 | 23 | 0 | 23 | N.A. |
2 | 03/09/2012 | 08/09/2012 | 5 | 10 | 23 | -13 | *length of iteration 2 is half of iteration 1 *difficulties in implementing neural network |