Reason for Change: Client Requested change in Queue logic
Sprint | Milestone | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Remarks |
---|---|---|---|---|---|---|
Sprint 1 | Queue User Interface, Location Based Services, View Map, View Queue Status | 8th October | 21st October | 8th October | 21st October | Completed |
Sprint 2 | Queue Management with Application Hearing Date Fixed, Ticket Generation | 22nd October | 4th Novermber | 22nd October | 4th Novermber | For Acceptance Presentation (5th November) |
Sprint 3 | Queue Timing, Queue UI,LBS Strategy Application | 17th December | 30th December | 17th December | 30th December | Completed |
Sprint 4 | Change of Readiness Status,Change of Adjournment Status | 31st December | 13th January | 31st December | 17th January | Completed |
Sprint 5 | Queue Admin Module, Push Notifications, Services | 14th January | 20th January | 17th January | 26th January | Completed |
Sprint 6 | Hearing List | 21st January | 30th January | 21st January | 31st January | Completed |
Sprint 7 | Security Add-Ons | 1st February | 6th February | 1st February | 6th February | Completed |
Sprint 8 | Modifications based on Functional Testing | 7th February | 9th February | 7th February | 9th February | Completed |
Sprint 9 | Modifications based on User Test(Paper prototypes) | 12th February | 14th February | 12th February | 15th February | Completed |
Sprint 10 | Predictive Algorithm,Fix changed requests based on unguided User Test, Way-Finder Research | 15th February | 20th February | 15th February | 20th February | Completed |
Sprint 11 | Predictive Algorithm,Fix changed requests based on Management Observations, Way-Finder Research | 21st February | 27th February | 21st February | 27th February | Completed |
Sprint 12 | Way Finder,Predictive Algorithm,Fix change requests based on UAT 1 | 28th February | 14th March | 28th February | 14th March | Completed |
Sprint 13 | Way Finder,Predictive Algorithm back-testing, Changes in Queue Logic | 18th March | 1st April | 18th March | 13th April | Completed |
Sprint 14 | Way Finder Changes based on User Acceptance Test 2 with Registrars | 2nd April | 13th April | 2nd April | 19th April | Completed |
Contents
Development Schedule v3
Reason for change: Supervisor advised to present on way finder before mid terms.
Sprint | Milestone | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Remarks |
---|---|---|---|---|---|---|
Sprint 1 | Queue User Interface, Location Based Services, View Map, View Queue Status | 8th October | 21st October | 8th October | 21st October | Completed |
Sprint 2 | Queue Management with Application Hearing Date Fixed, Ticket Generation | 22nd October | 4th Novermber | 22nd October | 4th Novermber | For Acceptance Presentation (5th November) |
Sprint 3 | Queue Timing, Queue UI,LBS Strategy Application | 17th December | 30th December | 17th December | 30th December | Completed |
Sprint 4 | Change of Readiness Status,Change of Adjournment Status | 31st December | 13th January | 31st December | 17th January | Completed |
Sprint 5 | Queue Admin Module, Push Notifications, Services | 14th January | 20th January | 17th January | 26th January | Completed |
Sprint 6 | Hearing List | 21st January | 30th January | 21st January | 31st January | Completed |
Sprint 7 | Security Add-Ons | 1st February | 6th February | 1st February | 6th February | Completed |
Sprint 8 | Modifications based on Functional Testing | 7th February | 9th February | 7th February | 9th February | Completed |
Sprint 9 | Modifications based on User Test(Paper prototypes) | 12th February | 14th February | 12th February | 15th February | Completed |
Sprint 10 | Predictive Algorithm,Fix changed requests based on unguided User Test, Way-Finder Research | 15th February | 20th February | 15th February | 20th February | Completed |
Sprint 11 | Predictive Algorithm,Fix changed requests based on Management Observations, Way-Finder Research | 21st February | 27th February | 21st February | 27th February | Completed |
Sprint 12 | Way Finder,Predictive Algorithm,Fix change requests based on UAT 1 | 28th February | 14th March | 28th February | 14th March | Completed |
Sprint 13 | Way Finder,Predictive Algorithm back-testing | 18th March | 1st April | |||
Sprint 14 | Way Finder Changes based on User Acceptance Test 2 with Registrars | 2nd April | 13th April |
Development Schedule v2
Reason for change: Client testing has been changed from a 1 day event at Supreme Court to multiple unguided users
Sprint | Milestone | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Remarks |
---|---|---|---|---|---|---|
Sprint 1 | Queue User Interface, Location Based Services, View Map, View Queue Status | 8th October | 21st October | 8th October | 21st October | Completed |
Sprint 2 | Queue Management with Application Hearing Date Fixed, Ticket Generation | 22nd October | 4th Novermber | 22nd October | 4th Novermber | For Acceptance Presentation (5th November) |
Sprint 3 | Queue Timing, Queue UI,LBS Strategy Application | 17th December | 30th December | 17th December | 30th December | Completed |
Sprint 4 | Change of Readiness Status,Change of Adjournment Status | 31st December | 13th January | 31st December | 17th January | Completed |
Sprint 5 | Queue Admin Module, Push Notifications, Services | 14th January | 20th January | 17th January | 26th January | Completed |
Sprint 6 | Hearing List | 21st January | 30th January | 21st January | 31st January | Completed |
Sprint 7 | Security Add-Ons | 1st February | 6th February | 1st February | In Progress | |
Sprint 8 | Modifications based on Functional Testing | 7th February | 9th February | NA | ||
Sprint 9 | Modifications based on User Test(Paper prototypes) | 12th February | 14th February | NA | ||
Sprint 10 | Predictive Algorithm,Fix changed requests based on unguided User Test | 15th February | 20th February | NA | ||
Sprint 11 | Predictive Algorithm,Fix changed requests based on Management Observations | 21st February | 27th February | NA | ||
Sprint 12 | Way Finder,Analytics Predictive Algorithm,Fix change requests based on Registrars Comments | 28th February | 14th March | NA | ||
Sprint 13 | Way Finder,Analytics Dash Board,Changes based on Private Law Firms comments | 18th March | 1st April | NA | ||
Sprint 14 | Way Finder | 2nd April | 13th April | NA |
Development Schedule v1
Sprint | Milestone | Planned Start Date | Planned End Date | Actual Start Date | Actual End Date | Remarks |
---|---|---|---|---|---|---|
Sprint 1 | Queue User Interface, Location Based Services, View Map, View Queue Status | 8th October | 21st October | 8th October | 21st October | Completed |
Sprint 2 | Queue Management with Application Hearing Date Fixed, Ticket Generation | 22nd October | 4th Novermber | 22nd October | 4th Novermber | For Acceptance Presentation (5th November) |
Sprint 3 | Queue Timing, Queue UI,LBS Strategy Application | 17th December | 30th December | 17th December | 30th December | Completed |
Sprint 4 | Change of Readiness Status,Change of Adjournment Status | 31st December | 13th January | 31st December | 17th January | Completed |
Sprint 5 | Queue Admin Module, Push Notifications, Services | 14th January | 20th January | 17th January | 26th January | Completed |
Sprint 6 | Hearing List | 21st January | 30th January | 21st January | KIV- Client to get back with RSS specs | |
Sprint 7 | Security Add-Ons | 1st February | 6th February | NA | ||
Sprint 8 | Modifications based on T1 | 7th February | 9th February | NA | ||
Sprint 9 | Modifications based on T2 | 13th February | 18th February | NA | ||
Sprint 10 | Analytics | 28th February | 15th March | NA | ||
Sprint 11 | Way Finder | 18th March | 30th March | NA | ||
Sprint 12 | Debug based on Test | 8th April | 13th April | NA |