Task/function/features | Status | Confident Level(%) | Comment/Remarks |
Speech Recognition & Pre-assignment | Completed | 100 | Done |
User Interface & Learning Dashboard (Phase 1) | Completed | 100 | Done (Changes have been made to these following the completion of all the other functionalities) |
Text Association | Completed | 100 | Done |
Basic Functions (Login/logout, register) | Completed | 100 | Done |
Content Development | Completed | 100 | Done |
Grammar capability | Completed | 100 | Done |
Resource | Completed | 100 | Done |
User Profile | Completed | 100 | Done |
User Interface & Learning Dashboard (Final Phase) | Completed | 100 | Done |
Convert Questions to PDF & download function | Completed | 100 | Done |
Game | Completed | 100 | Done |