Planned Development Iteration

S/N Planned For Which Milestone? Functions Details


01
Planned for Mid-Term
Silverlight Video Banner
  • Hard coded data will be used
  • Upload function will be added after mid-term review
02
Planned for Mid-Term
Full User functionalities
  • Add/Delete/Ban/Mute Users
  • Password Change/Reset
  • Profile Page Display
03
Planned for Mid-Term
Wall Feature
  • Delete/Edit Function for Admin, Delete Function for R-Users
  • Share to FB+Twitter
  • Rating – Like/Dislike
04
Planned for Mid-Term
Badge System
  • Create New Custom Badge
  • Manually Assign Badge
  • Enter Codeword for Badge
05
Planned for Mid-Term
Themeing
  • Main Page
  • Wall
  • Profile Page
06
Planned for Mid-Term
Themeing
  • Main Page
  • Wall
  • Profile Page
07
Planned for Final
Silverlight
  • Upload Functions
  • Create Highlight Videos Function
  • Bootstrap Client Data
08
Planned for Final
Badge System
  • Wall Behaviour Badges
  • FB/Twitter link up badges (might change)
  • Login Time Badges (might change)
  • Bootstrap Client Data


  • Iteration 1 – Week 1/2
  • Iteration 2 – Week 3/4
  • UAT done in Week 5
  • Mid-Term preparation/rehearsal in Week 6
  • UAT done in Week 11/12
  • Final preparation in Week 12/13


This document contains FISSION1 Project Schedule:
Media: FISSION1_-_FYP_Schedule-v4-.pdf