HeaderSIS.jpg

IS480 Team wiki: 2010T2 B.I. JOE

From IS480
Jump to navigation Jump to search

FYP Logo.png

Team B.I.JOE

Roles & Responsibilities

Member(s) Roles Responsibilities
Gary Tan Ying Da Project Manager, Liaison Officer, Tester Liaison, Tester, Schedule tracking, Assistant Programmer for Secondary Visualization
Ng Wei Quan Assistant Project Manager Administrative duties; minutes, Update Wikipedia, Risk mitigation, Lead Programmer for Secondary Visualization
Marcus Yap Interface Designer Front-end design: user interface and graphics; Interface Designer
Isaac Lim Code Developer Lead Programmer for Primary Visualization, Debug and Code Integration
Sim Sing Hong Code Developer Back-end design: Database Engineer, Debugger, Assistant Programmer for Primary Visualization

FYP Supervisor

Zhu Feida, Assistant Professor of Information Systems

Project Overview

Stakeholders

Sponsor Dr. Kam Tin Seong
Practice Associate Professor
School of Information Systems

Nicholas Tan
Director IT Application
IDS Group, Malaysia
Client Nicholas Tan
Director IT Application
IDS Group, Malaysia

nicholas.tan@idsgroup.com
Advisors/Practitioners Merchanising and Distribution Services Department
IDS Group

Background

IDS provide outsourced services to various clients. They generate analysis reports using their own applications and emailing them daily, weekly and monthly. IDS has selectively shared information on the web but now wishes to develop a portal dashboard that converts online data into analysis reports that provides an immediate picture of the situation and facilitates rapid decision making.

Storyboard

Storyboard 01.jpg Storyboard 02.jpg Storyboard 03.jpg Storyboard 04.jpg Storyboard 05.jpg Storyboard 06.jpg

Objectives

To create data visualisation for IDS employees to extract information and make analysis through better visual representation of data.

Project Management

Metric and Risk Assessment

  • Schedule Metric

Schedule metric v1.jpg Schedule metric2 v1.jpg

  • School Workload Metric
  • Bug Metric
  • Usability Impact Assessment

Project Status

  • Finished Phase 1, preparing for Acceptance

Progress Summary

Important Dates

  • Start 16 May 10 & 3 Oct 10 (3 months before)
  • Proposal 16 Jun 10 (29 teams) & 3 Nov 10 (2 months before)
  • Acceptance 9 Aug 10 (26 accepted) & 27 Dec 10 (1 week before)
  • Registration 16 Aug 10 & 3 Jan 11 (1st day of class)
  • Midterm 27 Sep 10 & 14 Feb 11 (week 7)
  • Poster 8 Nov 10 & 28 Mar 11 (week 13)
  • Final presentation 22-28 Nov 10 & 11-17 Apr 11 (week 15)
  • Finals 28 Nov 10 & 17 Apr 11

Documentation

Project Proposal

Proposal

Project Schedule

Latest MS Project

Acceptance