== Organization Overview ==
+
== Project Overview ==
==== Friends of the Disabled Society (FDS) ====
+
=== Whom are we working for? ===
FDS is a non-profit organization that establish programs liaised between the able-bodied and disabled friends together with help from members and well-wishers. Among these programs, the Skills Enrichment Program currently conducts training to advance the skills and creativity of the disabled people in handicraft and jewelry making.
+
Our team is working for a non-profit organization, named '''Friends of The Disabled Society (FDS)'''.  FDS establishes programs that brings a bridge between the able bodies and disabled friends together with the help from members and well-wishers. Among those programs, the Skills Enrichment Program, which our project's focus is on, currently conducts training to advance the skills and creativity of the disabled friends in handicraft and jewelry making.
 +
 
 +
=== Problem ===
 +
Regarding the Skills Enrichment Program, FDS currently has a shopping website hosted on a blog only.  The problem comes in as this blog is not designed for disabled friends; so, they have to go through multiple steps just to upload one product.  Moreover, the current website cannot assist FDS in processing orders, managing products and generating reports. With all these limitations and more, the potential collaboration between the customers and disabled people is hindered.
 +
 
 +
=== Solution ===
 +
Our team believes that applications that involve interactions with disabled friends should be more effective than this while being kept simple.  Thus, we are determined to come up with a proper and professional e-commerce system that comes together with a simple, tidy and easy-to-manage back-end interface especially designed for the disabled friends.  This system will also be well equipped with all the functions that are necessary and useful for the users.  The detailed functions each user can do with the application can be seen in Use Cases section below.
 +
 
 +
=== Use Cases ===
 +
Here, you can see what each user can do with our system.  In the use cases, you will see circles of different colors.
 +
* White Circles: As-is functions from OpenCart with very minor modifications made
 +
* Green Circles: Functions with major modifications made
 +
* Yellow Circles: Brand new functions
 +
==== Customer ====
 +
[[Image:CustomerUseCase.jpg]] <br><br>
  
==== Problem ====
+
==== Admin Assistant ====
The organization does not have an e-commerce system where the disabled people can upload and sell their products conveniently with minimum supervision.
+
[[Image:AAUseCase.jpg]] <br><br>
  
==== Solution ====
+
==== Top Admin ====
We will build an e-commerce system with simple, tidy and easy-to-manage back-end interface especially designed for the disabled people to sell their products.
+
The Top Admin can do everything the Admin Assistant does.  On top of that, the Top Admin can do some additional tasks which are represented by red arrows.<br>
 +
[[Image:TopAdminUseCase.jpg]] <br>
  
== Who is in? ==
+
== Stakeholders ==
==== Supervisor ====
+
=== Supervisor ===
 
'''''[http://www.sis.smu.edu.sg/faculty/infosys/kevinsteppe.asp Kevin Steppe]'''''
 
'''''[http://www.sis.smu.edu.sg/faculty/infosys/kevinsteppe.asp Kevin Steppe]'''''
  
==== Team eNable ====
+
=== Sponsor/Client ===
 +
* Ms. S Roogmanny (Executive Director, Friends of Disabled Society)
 +
* Mr. Joel Chiang (IT Manager, Jweeb Solutions Group)
 +
 
 +
=== Team eNable ===
 
# '''''[mailto:erene.ong.2008@sis.smu.edu.sg Erene ONG Yiling]'''''
 
# '''''[mailto:erene.ong.2008@sis.smu.edu.sg Erene ONG Yiling]'''''
 
# '''''[mailto:tdkhine.2007@sis.smu.edu.sg KHINE Tharaphe Din]'''''
 
# '''''[mailto:tdkhine.2007@sis.smu.edu.sg KHINE Tharaphe Din]'''''
Line 21: Line 40:
 
# '''''[mailto:lumon.kyaw.2008@sis.smu.edu.sg Lu Mon KYAW]'''''
 
# '''''[mailto:lumon.kyaw.2008@sis.smu.edu.sg Lu Mon KYAW]'''''
 
# '''''[mailto:soethetaung.2008@sis.smu.edu.sg Soe Thet AUNG]'''''
 
# '''''[mailto:soethetaung.2008@sis.smu.edu.sg Soe Thet AUNG]'''''
 +
<br>
  
==== Sponsor/Client ====
+
== Project Management ==
* Ms. S Roogmanny (Executive Director, Friends of Disabled Society)
+
Our team will use SCRUM project management framework.
* Mr. Joel Chiang (IT Manager, Jweeb Solutions Group)
 
 
 
== Project Overview ==
 
==== Project Description ====
 
FDS currently has a shopping website hosted on a blog. However, it, firstly, is not designed for disabled people and so they have to go through multiple steps to sell their products. Secondly, the current website cannot assist the buyers and sellers in processing orders, managing products and generating reports.
 
  
With all these limitations and more, the potential of collaboration between the customers and disabled people is hindered. Our team believes that applications that involve interactions with a disabled person should be more effective while being kept simple. Therefore, we are determined to introduce a proper and professional eCommerce website that can help solve these problems.  
+
=== SCRUM Documents ===
 +
'''''[[Media:Enable_productback.docx|Product Backlog]]''''' serves as a primary document for the client and the team to look into the list of all the functionalities that are to be implemented. The functionalities are listed in order of their priority. <br>
 +
'''''[[Media:Enable_sprintback.docx|Sprint Backlog]]''''' is a subset of Product Backlog containing a detailed breakdown of functionalities into tasks for each of the sprints.
  
Through this project, our team aims to create an online shopping system for the Skills Enrichment Program. Using this system, the disabled friends can manage and sell conveniently the handmade gifts they make independently. Buyers can search and purchase the products. Moreover, people can spread the product news by sharing it through their Facebook walls and Twitter feeds. We will keep the back-end interface simple and user friendly so that it will be easy for the disabled friends to employ. The system will also generate sales reports for the organization.
+
=== Project Schedule ===
 +
Here, you can see our '''''[[Media:Enable_PlannedSchedule.docx|Planned Schedule]]''''' and '''''[[Media:Enable_ActualSchedule.docx|Actual Schedule]]''''' of the whole project. As all the sprints have a fixed length of 15 days, any scope or requirement change throughout the project did not have an impact on the start date or end date of the sprints. It only affected the iterations. The changes in dates and additional tasks added are highlighted in red in the Actual Schedule. The comparison of the two schedules over time can also be seen on our '''''[[Team eNable - Midterm Wiki|Midterm Wiki]]''''' and '''''[[Team eNable - Final Wiki|Final Wiki]]''''' pages.
  
==== Use Cases ====
+
=== Roles & Responsibilities ===
[[Image:BuyerUseCase.jpg]] <br>
+
{| border="3"
[[Image:SellerUseCase.jpg]] <br>
 
[[Image:AdminUseCase.jpg]]
 
 
 
==== E-commerce system chosen ====
 
'''''[http://www.opencart.com/ OpenCart]'''''
 
 
 
== Project Management ==
 
==== Project Schedule and Milestones ====
 
[[Media:Enable_planneds.docx|Planned Schedule]]<br>
 
[[Media:Enable_actuals.docx|Actual Schedule]]
 
 
 
==== SCRUM Documents ====
 
[[Media:Enable_productback.docx|Product Backlog]]<br>
 
[[Media:Enable_sprintback.docx|Sprint Backlogs]]
 
 
 
==== Roles & Responsibilities ====
 
{| border="2"
 
 
|- style="background: silver; color: black"
 
|- style="background: silver; color: black"
! scope=col width="200" | Role
+
! scope=col width="100" | Member
! scope=col width="100" | Primary
+
! scope=col width="200" | Primary Role
 
! scope=col width="500" | Responsibilities
 
! scope=col width="500" | Responsibilities
 
|-  
 
|-  
! scope=row | Project Manager
+
! scope=row | Din
| Din
+
| <div style="text-align:center;">Project Manager</div>
| - Plan meeting agenda and milestones
+
| - Plan meeting agenda and milestones<br>
 
+
- Make sure the team is on the right track and in progress<br>
- Make sure the team is on the right track and in progress
 
 
 
 
- Resolve internal conflicts, if any
 
- Resolve internal conflicts, if any
 
|-
 
|-
! scope=row | Chief Programmer and Designer
+
! scope=row | Erene
| Erene || - Translate clients' requirements into functionalities
+
| <div style="text-align:center;">Chief Programmer</div>
 
+
| - Translate clients' requirements into functionalities<br>
 
- Integrate frontend design and backend logic
 
- Integrate frontend design and backend logic
 
- Create designs for user interface and update the design documentations accordingly
 
 
|-
 
|-
! scope=row | Chief Tester
+
! scope=row | Kyaw
| Kyaw || - Track and prioritize bugs
+
| <div style="text-align:center;">Chief Tester</div>
 
+
| - Track and prioritize bugs<br>
 
- Develop test plans to ensure a smooth application
 
- Develop test plans to ensure a smooth application
 
|-
 
|-
! scope=row | Database Administrator
+
! scope=row | Lu Mon
| Soe Thet || - Create and maintain the server and database tables
+
| <div style="text-align:center;">Chief Designer</div>
 +
| - Create designs for user interface
 
|-
 
|-
! scope=row | Public Relations
+
! scope=row | Soe Thet
| Lu Mon || - Communicate with all external parties
+
| <div style="text-align:center;">System Admin</div>
 +
| - Create and maintain the server and system database 
 +
|}
  
- Resolve external conflicts, if any
+
=== Project Risks ===
 +
The risks specific to our project at the initial state are as follows: <br>
 +
{| border="3"
 +
|- style="background: silver; color: black"
 +
! scope=col width="200" | Risks
 +
! scope=col width="100" | Likelihood
 +
! scope=col width="100" | Impact
 +
! scope=col width="100" | Risk Level
 +
! scope=col width="400" | Mitigation Plans
 +
|-
 +
| Lack of experiences in php resulting a delay during application development
 +
| Moderate
 +
| High
 +
| High
 +
| Do research on php and help each other to be more familiar with it in a shorter period of time
 +
|-
 +
| No prior knowledge of OpenCart
 +
| High
 +
| High
 +
| High
 +
| Allocate  some time to familiarize with the new system
 +
|-
 +
| Look and feel of the application does not meet the end users’ needs
 +
| Moderate
 +
| Moderate
 +
| Moderate
 +
| Perform UAT with the real end users and gather feedback to ensure a design that appeals to them
 +
|-
 +
| Maintenance of the system by the client
 +
| High
 +
| Low
 +
| Moderate
 +
| Schedule some trainings for the client/admin of the system at the end of the project
 
|}
 
|}
  
== Presentations ==
+
=== Quality Assurance ===
[[Media:Enable_acceptance.pptx|Acceptance Presentation]]<br>
+
To make sure that our project quality is kept at its best and that the application built meets the client's expectations, we will perform a number of User Acceptance Tests with the client and real end users throughout the project.  Moreover, we will also use Schedule Metric and Bug Metric to track the team's productivity and quality of work done.
[[Media:Enable_midterm.pptx|Midterm Presentation]]<br>
+
 
Final Presentation
+
== Go To ==
 +
'''''[[Team eNable - Midterm Wiki|Midterm Wiki]]'''''<br>
 +
'''''[[Team eNable - Final Wiki|Final Wiki]]'''''

Latest revision as of 23:57, 28 November 2010

eNable

Project Overview

Whom are we working for?

Our team is working for a non-profit organization, named Friends of The Disabled Society (FDS). FDS establishes programs that brings a bridge between the able bodies and disabled friends together with the help from members and well-wishers. Among those programs, the Skills Enrichment Program, which our project's focus is on, currently conducts training to advance the skills and creativity of the disabled friends in handicraft and jewelry making.

Problem

Regarding the Skills Enrichment Program, FDS currently has a shopping website hosted on a blog only. The problem comes in as this blog is not designed for disabled friends; so, they have to go through multiple steps just to upload one product. Moreover, the current website cannot assist FDS in processing orders, managing products and generating reports. With all these limitations and more, the potential collaboration between the customers and disabled people is hindered.

Solution

Our team believes that applications that involve interactions with disabled friends should be more effective than this while being kept simple. Thus, we are determined to come up with a proper and professional e-commerce system that comes together with a simple, tidy and easy-to-manage back-end interface especially designed for the disabled friends. This system will also be well equipped with all the functions that are necessary and useful for the users. The detailed functions each user can do with the application can be seen in Use Cases section below.

Use Cases

Here, you can see what each user can do with our system. In the use cases, you will see circles of different colors.

  • White Circles: As-is functions from OpenCart with very minor modifications made
  • Green Circles: Functions with major modifications made
  • Yellow Circles: Brand new functions

Customer

CustomerUseCase.jpg

Admin Assistant

AAUseCase.jpg

Top Admin

The Top Admin can do everything the Admin Assistant does. On top of that, the Top Admin can do some additional tasks which are represented by red arrows.
TopAdminUseCase.jpg

Stakeholders

Supervisor

Kevin Steppe

Sponsor/Client

  • Ms. S Roogmanny (Executive Director, Friends of Disabled Society)
  • Mr. Joel Chiang (IT Manager, Jweeb Solutions Group)

Team eNable

  1. Erene ONG Yiling
  2. KHINE Tharaphe Din
  3. KYAW Zin Hein
  4. Lu Mon KYAW
  5. Soe Thet AUNG


Project Management

Our team will use SCRUM project management framework.

SCRUM Documents

Product Backlog serves as a primary document for the client and the team to look into the list of all the functionalities that are to be implemented. The functionalities are listed in order of their priority.
Sprint Backlog is a subset of Product Backlog containing a detailed breakdown of functionalities into tasks for each of the sprints.

Project Schedule

Here, you can see our Planned Schedule and Actual Schedule of the whole project. As all the sprints have a fixed length of 15 days, any scope or requirement change throughout the project did not have an impact on the start date or end date of the sprints. It only affected the iterations. The changes in dates and additional tasks added are highlighted in red in the Actual Schedule. The comparison of the two schedules over time can also be seen on our Midterm Wiki and Final Wiki pages.

Roles & Responsibilities

Member Primary Role Responsibilities
Din
Project Manager
- Plan meeting agenda and milestones

- Make sure the team is on the right track and in progress
- Resolve internal conflicts, if any

Erene
Chief Programmer
- Translate clients' requirements into functionalities

- Integrate frontend design and backend logic

Kyaw
Chief Tester
- Track and prioritize bugs

- Develop test plans to ensure a smooth application

Lu Mon
Chief Designer
- Create designs for user interface
Soe Thet
System Admin
- Create and maintain the server and system database

Project Risks

The risks specific to our project at the initial state are as follows:

Risks Likelihood Impact Risk Level Mitigation Plans
Lack of experiences in php resulting a delay during application development Moderate High High Do research on php and help each other to be more familiar with it in a shorter period of time
No prior knowledge of OpenCart High High High Allocate some time to familiarize with the new system
Look and feel of the application does not meet the end users’ needs Moderate Moderate Moderate Perform UAT with the real end users and gather feedback to ensure a design that appeals to them
Maintenance of the system by the client High Low Moderate Schedule some trainings for the client/admin of the system at the end of the project

Quality Assurance

To make sure that our project quality is kept at its best and that the application built meets the client's expectations, we will perform a number of User Acceptance Tests with the client and real end users throughout the project. Moreover, we will also use Schedule Metric and Bug Metric to track the team's productivity and quality of work done.