Line 47: | Line 47: | ||
<!--Content Start --> | <!--Content Start --> | ||
+ | <br> | ||
+ | The team will evaluate the change by taking the following steps | ||
+ | [[Image:Team_Elements_ChangeMgmt.png|550px|center]] | ||
+ | {| class="wikitable" style="background-color:#FFFFFF;" | ||
+ | |- | ||
+ | ! style="color:white; background-color:#4B1680;" | Priority Rating | ||
+ | ! style="color:white; background-color:#4B1680;" | Decision | ||
+ | ! style="color:white; background-color:#4B1680;" | Action | ||
+ | |||
+ | |- | ||
+ | | 0 | ||
+ | | Reject | ||
+ | | Inform client about rejection of change | ||
+ | |- | ||
+ | | 1 | ||
+ | | Low | ||
+ | | Functions can be added to tertiary/good-to-have functions | ||
+ | |- | ||
+ | | 2 | ||
+ | | Medium | ||
+ | | Discuss with client to rescope the project. Reduce current functionalities to cater for change. Reschedule project accordingly. | ||
+ | |- | ||
+ | | 3 | ||
+ | | High | ||
+ | | To be done immediately. PM is to reschedule tasks to include new function. | ||
+ | |} | ||
<!--Content End --> | <!--Content End --> |
Revision as of 13:09, 22 October 2015
Project Schedule | Schedule Metrics | Bug Metrics | Risk Management | Change Management |
The team will evaluate the change by taking the following steps
Priority Rating | Decision | Action |
---|---|---|
0 | Reject | Inform client about rejection of change |
1 | Low | Functions can be added to tertiary/good-to-have functions |
2 | Medium | Discuss with client to rescope the project. Reduce current functionalities to cater for change. Reschedule project accordingly. |
3 | High | To be done immediately. PM is to reschedule tasks to include new function. |