The team will evaluate the change by taking the following steps
 +
[[Image:Team_Elements_ChangeMgmt.png|550px|center]]
  
 +
{| class="wikitable" style="background-color:#FFFFFF;"
 +
|-
 +
! style="color:white; background-color:#4B1680;" | Priority Rating
 +
! style="color:white; background-color:#4B1680;" | Decision 
 +
! style="color:white; background-color:#4B1680;" | Action
 +
 +
|-
 +
| 0
 +
| Reject
 +
| Inform client about rejection of change
 +
|-
 +
| 1
 +
| Low
 +
| Functions can be added to tertiary/good-to-have functions
 +
|-
 +
| 2
 +
| Medium
 +
| Discuss with client to rescope the project. Reduce current functionalities to cater for change. Reschedule project accordingly.
 +
|-
 +
| 3
 +
| High
 +
| To be done immediately. PM is to reschedule tasks to include new function.
 +
|}
 
<!--Content End -->
 
<!--Content End -->

Revision as of 13:09, 22 October 2015

Team Elements Logo.jpg


Team Elements Home.png   HOME

 

Team Elements AboutUs.png   ABOUT US

 

Team Elements PrjOverview.png   PROJECT OVERVIEW

 

Team Elements PrjMgmt.png   PROJECT MANAGEMENT

 

Team Elements Documentation.png   DOCUMENTATION

Project Schedule Schedule Metrics Bug Metrics Risk Management NavigationElements.png Change Management


The team will evaluate the change by taking the following steps

Team Elements ChangeMgmt.png
Priority Rating Decision Action
0 Reject Inform client about rejection of change
1 Low Functions can be added to tertiary/good-to-have functions
2 Medium Discuss with client to rescope the project. Reduce current functionalities to cater for change. Reschedule project accordingly.
3 High To be done immediately. PM is to reschedule tasks to include new function.