Difference between revisions of "Dpenz Midterm Wiki"
Line 391: | Line 391: | ||
|} | |} | ||
− | <br> | + | <br> |
− | |||
=== <font face="Droid Sans" color="#ff9a00">Project Metrics</font> === | === <font face="Droid Sans" color="#ff9a00">Project Metrics</font> === | ||
Please view our metrics on our [https://wiki.smu.edu.sg/is480/IS480_Team_wiki%3A_2013T2_D%27PENZ_Metrics_Management Metrics Management page] | Please view our metrics on our [https://wiki.smu.edu.sg/is480/IS480_Team_wiki%3A_2013T2_D%27PENZ_Metrics_Management Metrics Management page] | ||
− | <Br | + | <Br> |
=== <font face="Droid Sans" color="#ff9a00">Project Risks</font> === | === <font face="Droid Sans" color="#ff9a00">Project Risks</font> === |
Revision as of 16:58, 23 February 2014
Home | Our Team | Project Overview | Project Management | Project Documentation |
Project Progress Summary
Guideline(to be deleted when complete): https://wiki.smu.edu.sg/is480/IS480_Midterm_Wiki
Midterm Slides:
Deployment Site Link: IPS
Login Details
User Role | Name | XPID | Password |
---|---|---|---|
Functional Owner | Mandy | 9002 | monkey |
Procurement Staff | Tom | 9003 | monkey |
Manager | Marlie | 9112 | monkey |
C-level | Dany | 9113 | monkey |
Project Highlights
- Deployment pushed back due to long time needed to get through compliance process in bank.
- Cannot connect to Active Directory (AD).
- Remove function: Single sign on, replace with password login process.
- Remove function: Connect to AD, replace with function of Admin Panel to add new users.
- Currently deployed on IS480 server with external IP for clients to use it.
- Delay in report function due to insufficient information from our client.
- Delay in Approval function due to change in approval flow after client test.
- Delays in communication due to the festive season (Christmas, New Year and Lunar New Year).
Project Management
Project Status
Task/function/features, etc | Status | Confident Level (0-1) | Comment |
CRU Projects | Fully deployed and tested 100% | 1 | Malique, Ching Png |
Search Project | Fully deployed and tested 100% | 1 | Nicole |
Edit PAF Template | Fully deployed and tested 100% | 1 | Dex, Ching Png |
Customizable PAF Template Fields & Phases | Fully deployed and tested 100% | 1 | Dex, Ching Png |
Audit Log | Fully deployed and tested 100% | 1 | Malique |
CRU Supplier Information | Fully deployed and tested 100% | 1 | Nicole, Zoey |
Generate Report | Fully deployed and tested 100% | 1 | Dex, Ching Png |
Approve Procurement | Fully deployed and tested 100% | 1 | Malique |
Notification | Fully deployed and tested 100% | 1 | Zoey, Ching Png |
Admin Panel | 0% Starting after midterm | 0.9 | Ching Png has started the planning process |
Export Report | 0% Starting after midterm | 1 | Dex |
Export Project Details | 0% Starting after midterm | 1 | Malique |
View Past PAF Templates | 0% Starting in Sprint 8 | 1 | Dex |
Project Schedule (Planned vs Actual)
Between Acceptance and Midterm, everything has proceeded as planned, with some changes as mentioned in Project Highlights. Other changes have been logged in our change log. (Please see section on Change Management
We've had some delays with respect to our client as they were more busy the past months and did not have time to provide us with required information to proceed with some of our functions. We are currently 8 days behind in Sprint 6, and we will be trying to get back on track in Sprint 7 by putting in more work hours each day.
An overview of our project can be seen in our Project Schedule page. A detailed schedule is also available in the page.
Iterations | Planned | Actual | Comments | ||
1 | Define scope | 27 Aug 2013 | 27 Aug 2013 | ||
Create requirements list | 6 Sep 2013 | 6 Sep 2013 | |||
Create technical diagrams | 18 Sep 2013 | 18 Sep 2013 | |||
2 | Set up database, server | 21 Sep 2013 | 20 Sep 2013 | ||
View/edit projects | 24 Sep 2013 | 23 Sep 2013 | |||
Search Project | 24 Sep 2013 | 23 Sep 2013 | |||
Learn .NET C# | 1 Oct 2013 | 3 Oct 2013 | Training took longer than expected as the frameworks were relatively new and much research needed to be done. | ||
Port prototype from Java to .NET C# | 10 Oct 2013 | 16 Oct 2013 | Took longer time than expected as members were not familiar with .NET C# | ||
3 | Submit new project | 24 Oct 2013 | 24 Oct 2013 | ||
Proposal submission | 28 Oct 2013 | 28 Oct 2013 | |||
User Testing 1 | 29 Oct 2013 | 29 Oct 2013 | |||
Acceptance | 5 Nov 2013 | 5 Nov 2013 | |||
Edit PAF Template | Shifted to Sprint 4 | ||||
4 | Edit PAF Template | 14 Dec 2013 | 14 Dec 2013 | Shifted from Sprint 3 | |
Customizable Fields & Phases | 18 Dec 2013 | 20 Dec 2013 | Customizable fields were more technically complex than we expected during planning. | ||
Audit Log | 18 Dec 2013 | 18 Dec 2013 | Shifted from Sprint 5 | ||
Submit supplier | 18 Dec 2013 | 18 Dec 2013 | Shifted from Sprint 5 | ||
Approve Procurement | Shifted to Sprint 5 | ||||
Active Directory, Single Sign On | Pushed back due to delays in approval process from client (eventually we are replacing this function with Admin Panel to add in new users) | ||||
5 | UT2 | 27 Dec 2013 | 30 Dec 2013 | Clients were not free at the proposed time. | |
Generate report | 5 Jan 2014 | 20 Jan 2014 | Did not receive sufficient information from client to proceed with function. We created templated reports and proceeded with other functions while waiting for the information. | ||
Submit Supplier | Shifted to Sprint 4 | ||||
Search Supplier | 4 Jan 2014 | 9 Jan 2014 | Public holidays and festive season -- lesser working days. | ||
View Supplier | Shifted to Sprint 6 | ||||
Export Report | As there was a huge delay for Generate Report function, it would be too late to carry out this function in the same sprint, hence we decided to shift Export Report to a sprint that starts after Generate Report is complete (Sprint 7) | ||||
View Audit Log | Moved to Sprint 4 | ||||
Approve Procurement | 10 Jan 2014 | 10 Jan 2014 | Shifted from Sprint 4 | ||
6 | View, update supplier info | 26 Jan 2014 | 19 Jan 2014 | ||
View past PAF templates | Low priority. Will complete in Sprint 8 after Admin Panel. | ||||
UT3 | 27 Jan 2014 | 27 Jan 2014 | |||
UT4 | 7 Feb 2014 | 7 Feb 2014 | |||
Notifications | 5 Feb 2014 | 18 Feb 2014 | Insufficient resources as we were also preparing for UT3, UT4 and generate report. | ||
Customizable phases | Completed in Sprint 4 together with Edit PAF Template. | ||||
Export project details | Shift to Sprint 7 |