==Project Management==
 
==Project Management==
  
 
===Project Status===
 
  
 
== Project Status ==
 
== Project Status ==

Revision as of 18:59, 13 April 2014

Project Progress Summary

Progress

100% of the project is completed!

  • All functionalities completed!
  • Completed 12 out of 12 iterations


3 tests have been held

  • Heuristics Test: January 20 - 24
  • Usability Test 1: February 13 - 14
  • Usability Test 2: March 31 - April 4

System is deployed on the live server that OSL will be using in the future!

Project Timeline

AAN-Brief-Schedule-Final.png

Detailed schedule can be found here!

Project Highlights

Project Management

Project Status

Project Status
Module Function Status Confidence Level Deployment status
CORE Register for LMS
Register Not Completed 1 ×
Sign in
Sign in Completed 1
Booking Management
Add Booking Completed 1
View Booking Completed 1
Edit Booking Removed from functionalities under request of client 1 -
Delete Booking Removed from functionalities under request of client 1 -
Paying for Booking Completed 1
Locker Management
Add Lockers Completed 1
View Lockers Completed 1
Edit Lockers Completed 1
Delete Lockers Completed 1
Search for Lockers
Search Lockers Completed 1
Feedback Management
Report faulty locker Completed 1
View faulty locker reports Completed 1
Update faulty locker status Completed 1
Submit feedback Completed 1
View feedback Completed 1
Update feedback Completed 1
Delete feedback Completed 1
Locker Maintenance Account Management
Add Maintenance team Completed 1
View Maintenance team Completed 1
Edit Maintenance team Completed 1
Delete Maintenance team Completed 1
Statistics Dashboard
View Dashboard Completed 1
Booking Window Management
Set/Open/Close Booking Window timing Completed 1
Set/Edit Booking Timeframe Completed 1
Messaging Management
Send Message Completed 1
Delete Message Completed 1
SECONDARY iPhone App Development
Add locker bookings Completed 1
View Locker Completed 1
Report faulty lockers Completed 1
View map Completed 1
Android App Development
Add locker bookings Completed 1
View Locker Completed 1
Report faulty lockers Completed 1
View map Completed 1

For more information of the respective functions, visit AAN_Project_Management#Project_Status here!

Project Schedule (Plan Vs Actual):

Project Metrics

Schedule Metrics

To know how we calculate our schedule metrics, please refer to this!


For more information regarding Team AAN's mitigation plan, please refer to here!


Bug Metrics

To know how we calculate our bug metrics, please refer to this!

For more information regarding Team AAN's exact bugs, please look here!

Project Risks

S/N Risk Statement Consequence Likelihood Impact Level Contingency Plan

For the complete set of risks we face since the conception of project, please visit here! More information regarding how we measure our risks can also be found on that page.

Technical Complexity

Usability

Scalability

Flexibility

Quality of product

Intermediate Deliverables

Stage Specification Modules
Project Management Minutes
Metrics
Requirements Story cards CRUD Customer, Trend Analytic
Analysis Use Case Use Case Diagram
Screen Shots Prototype
Design ER Model ER Model
System Architecture Diagram Architecture Diagram
Testing Heuristic Testing Heuristic Test Results
Usability Test Plan Test Plan
Usability Test 1 Results UT1 Results
Usability Test 2 Results UT2 Results

Deployment

Testing

There are three tests conducted for our system; one Heuristics and two Usability Testing.

In the Heuristics Testing, we aim to find out user's view towards the design of our application so that we can make changes accordingly and ensure that the final product will be of high quality and well-received by everyone.

Heuristics Info:Heuristics Testing


For our first usability test, we will like to find out how well can users navigate our system. This will allow us to further improve on our system and ensure that the end product will be something that is close to dummy proof. Also, since we will be catering the system to the entire SMU, students from other schools participated in our UT too to ensure that we have a diverse and somewhat balanced opinion.

Usability Test 1 Info:Usability Test 1


After our first usability test, we made changes to some parts of the system based on the feedbacks that we have. Furthermore, there is the addition of certain functionalities as well as the iPhone app. Therefore, the second usability test allows us to finetune our project and ensure that our final product will be something that OSL finds satisfactory. Similar to the previous UT, the majority of participants are SMU students since they are the one who will be mainly using the system.

Usability Test 2 Info:Usability Test 2

Reflection