Project Schedule

Zuersttimeline24112016.png

Change Log

Iteration Date Who initiated the change? Description Reason Accept/Reject Status
2 18th May 2016 Project Manager Breaking down modules further into smaller functionalities. To make it easier to assign task to the team members. Accept Closed
6 13th July 2016 Project Manager Extend the duration taken to complete Events Module by 2 days Some bugs found during UAT and it will take some time to be rectified Accept Closed
8 13th August 2016 Supervisor Swap the iteration that is scheduled for Report Generation with Import/Export function. After Acceptance, our X-factor was to have 200 imported contacts, 50 manually created contacts and 50 events in the systems by Mid-Terms. According to the original timeline, Import/Export was scheduled to be completed after Mid-Terms. Therefore, there was a need to reorder the plan for later iterations. Accept Closed
10 10th September 2016 Client Added Refined Search to the next iteration due to request from client Client felt that they needed a more comprehensive Search function due to the vast number of tables in the database Accept Closed
11 23th Septemeber 2016 Client Email Reminder Module to include "CC" function Client wanted to be able to keep Team Manager in the loop for events that were created. Accept Closed