Project Schedule
Change Log
Iteration | Date | Who initiated the change? | Description | Reason | Accept/Reject | Status |
---|---|---|---|---|---|---|
2 | 18th May 2016 | Project Manager | Breaking down modules further into smaller functionalities. | To make it easier to assign task to the team members. | Accept | Closed |
6 | 13th July 2016 | Project Manager | Extend the duration taken to complete Events Module by 2 days | Some bugs found during UAT and it will take some time to be rectified | Accept | Closed |
8 | 13th August 2016 | Supervisor | Swap the iteration that is scheduled for Report Generation with Import/Export function. | After Acceptance, our X-factor was to have 200 imported contacts, 50 manually created contacts and 50 events in the systems by Mid-Terms. According to the original timeline, Import/Export was scheduled to be completed after Mid-Terms. Therefore, there was a need to reorder the plan for later iterations. | Accept | Closed |
10 | 10th September 2016 | Client | Added Refined Search to the next iteration due to request from client | Client felt that they needed a more comprehensive Search function due to the vast number of tables in the database | Accept | Closed |
11 | 23th Septemeber 2016 | Client | Email Reminder Module to include "CC" function | Client wanted to be able to keep Team Manager in the loop for events that were created. | Accept | Closed |