Task metrics is used to measure the team's efficiency when completing tasks. This is used as an indicator to see if the team has overestimated or underestimated the complexity of the tasks.
Formula: Actual No. of Tasks Completed/Estimated No. of Tasks Completed
|
Point(s)
|
Description
|
TM < 80
|
1. Need for greater efficiency 2. Re-estimate time needed to perform tasks and consider delaying tasks if necessary
|
80 < TM <= 120
|
1. Fairly accurate estimation 2. Proceed as per norma
|
TM > 120
|
1. Efficient 2. Re-estimate time needed to perform tasks and consider bringing tasks forward
|
|