Schedule Metrics


What: Schedule metrics are used to measure the progress of project.
When: It is measured at the end of each iteration.
How: Planned number of days/Actual number of days

Score Action
SM <= 0.9 Team is behind the schedule. Effort required to complete is under-estimated.
  1. Inform Supervisor
  2. Re-estimate tasks for future iterations
  3. Deduct the number of days behind schedule from buffer days
  4. If there is no more buffer day, decide the functionalities to drop
0.9 < SM <= 1.1 Estimates are fairly accurate and team is on schedule.
SM > 1.1 Team is ahead of schedule. Effort required to complete is over-estimated.
  1. Inform Supervisor
  2. Re-estimate tasks for future iterations
  3. Add the number of days gained to buffer days



Schedule Metrics Table

Schedule Metrics Overview.png


Iteration Planned Duration (Days) Actual Duration (Days) Schedule Metric Score Action Taken Status
3 14 16 0.88 More time needed to complete suggest group function.

Follow up action: Schedule slip was presented during Acceptance presentation. No delay to overall schedule as there are no major function to be developed in Iteration 4, which was scheduled to be preparation for Acceptance. Supervisor was informed of the slip after project was Accepted.

Completed
7 14 16 0.88 More time needed to develop filter search function.

Follow up action: Supervisor informed about delay. More hours was put into developing the function. No major delay in overall schedule as PM scheduled only one function, birthday reminder, to be developed in Iteration 8 due to festive period.

Completed
11 14 17 0.82 More time needed to develop Hashtags.

Follow up action: Supervisor informed about delay. More hours was put into developing the function. No major delay in overall schedule.

Completed





Archived Schedule Metrics