Project Progress Summary

 MID-TERM SLIDE 

Status:
Project is on track, we have successfully deployed to the Apple appstore. We had delay in iteration 5 due to National Service commitments. We are looking to conduct more user testings to gain insights on what users require. Further details about our project can be found below.

Development Progress: 80%
Modules Completed: 9
Modules Remaining: 2
Deployed on: Apple appstore (click to visit download page)

Gen6 current.png
Gen6 milestone.png

Project Highlights:


Gen6 appstore.png
QR Code to App Store:
Gen6 qr.png

  • Accepted by Apple appstore on 12 February 2015
  • Rolling out version 1.2 by 28 February 2015


Project Management

Project Status:

Gen6 Progress.png

Project Schedule (Plan Vs Actual):

Gen6 newtimeline.png
Gen6 oldtimeline.png

  • Changes in timeline is due to scope changes.
  • Iterations affected: 4 - 12 (Excluding 5)

Project Scope:

Gen6 actualtournow.png Gen6 plannedtournow.png
Please refer to our change management for details on scope changes!

Project Metrics:

Schedule Metrics
Gen6 SM2.png


Bug Metrics
Gen6 bugcountchart.png
Task Metrics
Gen6 TM.png

Project Risks:

Risk Type Risk Likelihood Impact Metric Mitigation
Project Lack of guidance in project direction and advice about business model as mentor is unavailable High High A 1. Supervisor to act as interim mentor
2. Pitch idea to potential mentors
3. Change to a new mentor, Joshua Nair
Technical Lack of knowledge and experience in submission to Apple appstore, failing to publish on appstore will delay our MVP High Medium A 1. Conduct more testing to eliminate bugs
2. Read up on Apple app submission guidelines and ensure that our app is adhering to it
3. Submit early to the appstore to have buffer time to fix issues highlighted
Technical Parse database is shutting down and app is dependent on it High Medium A 1. Plan a migration strategy
2. Explore feasibility of other platform
3. Migrate to best suited platform

Technical Complexity:

Features Involved Description of Technical Complexity What is to be achieved as an end result
ImageProcessor A custom library is built to use multiple 3rd party libraries to enhance the IOS’s UIImagePicker Library’s features can individually modified from new codes or libraries.

Any module can use this library to run the functions together:

1.Select a image from device’s gallery/camera
2.Resize the image
3.Crop image on a square or circular frame
4.Compress the image
5.Output the image


Quality of Product

Intermediate Deliverables:

Stage Specification Modules
Project Management Minutes Internal, Supervisor & Mentor
Metrics Schedule, Bug & Task
Change Management Change Management
Risk Management Risk Management
Schedule Schedule
Scope Scope
Requirements Market Research Market Research
Analysis Diagrams Architecture & Use Case Diagram
Technologies Technologies
Design Design & Prototype UI Prototyping
Testing User Testing User Testing

Deployment:



Gen6 aa.png

Test Plan

UAT 01 Details


Results
Gen6 UATICON.png
Click on icon to view more

Details
Date: 2 Feb 2016
Location: SIS Sr 2-3
Duration: 12pm - 6pm

Number of Users
21 SMU Students, 8 Tourist, 5 Tour Guide


Device Tested
iPhone 6s Plus: 9
iPhone 6 Plus: 8
iPhone 6: 11
iPhone 5s: 4
iPhone 5: 2

Objective:
1. Identify any usability problems that a user might face
2. Identify any aesthetic or user interface problems that a user might face
3. Likelihood of users using mobile application to book tour (From a scale of 1 to 10) to increase by a scale of at least '2' after experiencing Knock Knock

UAT01 Documents
*Gen6 UAT01 Results
*Gen6 UAT01 Unguided TestingTask Document
*Gen6 UAT01 Guided Testing Task Document
*Gen6 UAT01 Stress Testing Task Document

Reflection

Xan.PNG
HW.PNG


Bren.PNG
Nic.PNG


Don.PNG
KK.PNG