Project Progress Summary
MID-TERM SLIDE
Status:
Project is on track, we have successfully deployed to the Apple appstore. We had delay in iteration 5 due to National Service commitments. We are looking to conduct more user testings to gain insights on what users require. Further details about our project can be found below.
Development Progress: 80%
Modules Completed: 9
Modules Remaining: 2
Deployed on: Apple appstore (click to visit download page)
Project Highlights:
- Accepted by Apple appstore on 12 February 2015
- Rolling out version 1.2 by 28 February 2015
Project Management
Project Status:
Project Schedule (Plan Vs Actual):
- Changes in timeline is due to scope changes.
- Iterations affected: 4 - 12 (Excluding 5)
Project Scope:
Please refer to our change management for details on scope changes!
Project Metrics:
Schedule Metrics
Bug Metrics
Task Metrics
Project Risks:
Risk Type | Risk | Likelihood | Impact | Metric | Mitigation |
Project | Lack of guidance in project direction and advice about business model as mentor is unavailable | High | High | A | 1. Supervisor to act as interim mentor 2. Pitch idea to potential mentors 3. Change to a new mentor, Joshua Nair |
Technical | Lack of knowledge and experience in submission to Apple appstore, failing to publish on appstore will delay our MVP | High | Medium | A | 1. Conduct more testing to eliminate bugs 2. Read up on Apple app submission guidelines and ensure that our app is adhering to it 3. Submit early to the appstore to have buffer time to fix issues highlighted |
Technical | Parse database is shutting down and app is dependent on it | High | Medium | A | 1. Plan a migration strategy 2. Explore feasibility of other platform 3. Migrate to best suited platform |
Technical Complexity:
Features Involved | Description of Technical Complexity | What is to be achieved as an end result |
ImageProcessor | A custom library is built to use multiple 3rd party libraries to enhance the IOS’s UIImagePicker | Library’s features can individually modified from new codes or libraries.
Any module can use this library to run the functions together: 1.Select a image from device’s gallery/camera
|
Quality of Product
Intermediate Deliverables:
Stage | Specification | Modules |
Project Management | Minutes | Internal, Supervisor & Mentor |
Metrics | Schedule, Bug & Task | |
Change Management | Change Management | |
Risk Management | Risk Management | |
Schedule | Schedule | |
Scope | Scope | |
Requirements | Market Research | Market Research |
Analysis | Diagrams | Architecture & Use Case Diagram |
Technologies | Technologies | |
Design | Design & Prototype | UI Prototyping |
Testing | User Testing | User Testing |
Deployment:
Test Plan
UAT 01 Details
Results
Click on icon to view more
Details
Date: 2 Feb 2016
Location: SIS Sr 2-3
Duration: 12pm - 6pm
Number of Users
21 SMU Students, 8 Tourist, 5 Tour Guide
Device Tested
iPhone 6s Plus: 9
iPhone 6 Plus: 8
iPhone 6: 11
iPhone 5s: 4
iPhone 5: 2
Objective:
1. Identify any usability problems that a user might face
2. Identify any aesthetic or user interface problems that a user might face
3. Likelihood of users using mobile application to book tour (From a scale of 1 to 10) to increase by a scale of at least '2' after experiencing Knock Knock
UAT01 Documents
*Gen6 UAT01 Results
*Gen6 UAT01 Unguided TestingTask Document
*Gen6 UAT01 Guided Testing Task Document
*Gen6 UAT01 Stress Testing Task Document
Reflection