Project Schedule | Risk Management | Metrics |
Bug Metrics | |||||
---|---|---|---|---|---|
Low (1 point) | Negligible. Minor user interface issues | ||||
Medium (2 point) | Function working but not exactly the way we want it to be. | ||||
High (5 points) | Application runs but some non-critical functionalities are not working | ||||
Critical (10 points) | Application or critical functionality is down / unnusable after a short period of time. Require fixing of bugs to continue |
Bug Score | Mitigation Action |
---|---|
Score <= 10 | Use buffer time to fix |
10 < Score <= 20 | Use planned debugging time to fix |
Score > 20 | Create a card to fix the bugs and stop development until bugs are fixed |