Project Schedule WP SubPlane.png Schedule Metrics Task Metrics Bug Metrics Risk Management Change Management

Simplified Project Schedule

We are currently at Iteration 13.
Iteration Date Milestones Status
1 22 Sept 2014 - 5 Oct 2014 - Completed
2 6 Oct 2014 - 19 Oct 2014 - Completed
3 20 Oct 2014 - 2 Nov 2014 Proposal (20 Oct 2014) Completed
4 3 Nov 2014 - 16 Nov 2014 Acceptance Slides (03 Nov 2014) Completed
5 15 Dec 2014 - 28 Dec 2014 - Completed
6 29 Dec 2014 - 11 Jan 2015 - Completed
7 12 Jan 2015 - 25 Jan 2015 Deployment(15 Jan 2015)

User Testing 2 (21 Jan 2015)

Completed
8 26 Jan 2015 - 08 Feb 2015 Beta Release (2 Feb 2015) Completed
9 09 Feb 2015 - 22 Feb 2015 Midterm slides (18 Feb 2015) Completed
10 23 Feb 2015 - 08 Mar 2015 - Completed
11 09 Mar 2015 - 23 Mar 2015 Deployment
Pitch Video
Completed
12 24 Mar 2015 - 06 Apr 2015 User Testing 3 (25 Mar 2015)
Poster Submission (01 Apr 2015)
Final Deployment (06 Apr 2015)
Completed
13 05 Mar 2015 - 22 Apr 2015 Finals (15 Apr 2015)
Poster Day (22 Apr 2015)
In Progress

project schedule

We are currently at Iteration 13.
WP Schedule Overview.jpg

Archived Schedule