IS480 Team wiki: 2015T1 Pied Piper Final Wiki

From IS480
Jump to navigation Jump to search

Pied Piper Logo.jpg

MAIN WIKI   MIDTERM WIKI   FINAL WIKI


Links and Slides

Project Progress Summary

Project Highlights

Project Challenges

Project Achievement

Project Management

Overall Project Timeline

Planned Schedule Vs Actual Schedule

Scope Change

Project Metrics

Schedule Metrics

Bug Metrics

Man Hours Calculation

Project Risks

Technical Complexity

Quality of Product

Project Deliverable

Quality Attributes

Deployment

User Testing

Reflection

Team Reflection

  • Learn about real world projects and the complexities associated
  • Learn new technologies
  • Learn to work as per a changing scope as specified by the client
  • Learn to coordinate within the team
  • Learn to improve an existing application and value add to our client
  • Learn to juggle the rest of our projects along with FYP

Individual Reflection

Ong Hui Qi:

  • Enhanced and improved on project management skills
  • Learnt to keep the team on track and informed of the happenings
  • Learnt to balance between gaining technical knowledge to understand developer’s concerns, and project management
  • Learnt to balance the needs of various stakeholders, with the team’s capability and schedule in mind

Song Rui:

  • Learnt the power of automated task runners to streamline build process
  • Learnt the importance of good modular backend structure
  • Learnt the importance of communication code collaboration
  • Learnt what it takes to maintain a responsive web design

Adrien

  • Learnt how to use a framework such as Hibernate to best manage presentation logic
  • Learnt how to negotiate with stakeholders and strike a balance between their expectations and what I can achieve
  • Learnt and understood industry best practices and design trends, and mimicked them for this project
  • Learnt importance of communication for code collaboration

Arnold

  • Learnt how to use a framework such as Hibernate to best manage presentation logic
  • Learnt how to negotiate with stakeholders and strike a balance between their expectations and what I can achieve
  • Learnt and understood industry best practices and design trends, and mimicked them for this project
  • Learnt importance of communication for code collaboration

Dina Heng

  • Enhanced and improved on project management skills
  • Learnt the nuances of a QA: When to and not to allow the developer to release application in order to meet deadline
  • Learnt to conduct user tests and gather feedback to deliver a quality application
  • Learnt to work closely with developers to meet deadlines