IS480 Team wiki: 2014T2 Try Hard User Test
HOME | TEAM TRY HARD | PROJECT DESCRIPTION | PROJECT MANAGEMENT | PROJECT DOCUMENTATION |
PROJECT DESCRIPTION | PROJECT MOTIVATION | PROJECT SCOPE | USER TESTS | DESIGN & PROTOTYPE | X-FACTOR |
Contents
UAT 1
Description
The objective of this user test is to ensure that the application developed is in sync with the collected requirements while addressing any miscommunicated requirements if any. The team will also take this opportunity to perform a heuristic test to ensure the application have implemented right design principles to facilitate easy interaction with the application.
This user test will be conducted on a face to face basis.
Testers
1. Sponsor
2. 4 x SIS dean's office admin staff
Functions tested (Admin functions)
1. Set availability and preferences deadline
2. Set interview dates
3. Set dates which should not have interview
4. Set interviewing users
5. Set constraints between users
Main Takeaways
1. Differences between users and an expert is generally acceptable <100%
2. Unavailable Dates might be too user-unfriendly
3. Unavailable Dates Calendar might be too rigid in selection of the dates
4. Users are generally pleased with the UI design & find it useful rating avg of approx 7
5. Tasks for UAT can be more simplified for users to carry out
Task Incurred
Priority | Changes | Severity | Expected Additional Man Hours | Iteration to Solve |
1 |
Remove accordion for date planning |
3 |
2 |
7 |
2 |
Include "drag and pull" function into interviewer selection page |
2 |
2 |
7 |
3 |
Add user guide |
2 |
4 |
12 |
Results
UAT 2
Admin
Interviewer
Combined with UAT3