IS480 Team wiki: 2014T1 Happy Sounds Metrics Management
Jump to navigation
Jump to search
HOME | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION | ABOUT US |
PROJECT SCHEDULE | METHODOLOGY | METRICS MANAGEMENT | RISK & ISSUE MANAGEMENT | MEETING MINUTES |
SCHEDULE METRICS | BUG METRICS |
---|
Calculation: SM SCORE = Planned number of days / Actual number of days * 100
SM Score | Action |
---|---|
SM<50 |
|
50<SM<=90 |
|
90<SM<=110 |
|
110<SM<=150 |
|
150<SM |
|
Overall Schedule Metrics Chart
Calculation of SM Score
Iteration | Planned Days | Actual Days | SM Score | Action |
---|---|---|---|---|
1 |
32 |
32 |
100 |
Proceed as normal |
2 |
26 |
26 |
100 |
Proceed as normal |
3 |
35 |
35 |
100 |
Proceed as normal |
4 |
13 |
12 |
108.33 |
Proceed as normal |
5 |
15 |
20 |
75 |
|
6 |
11 |
14 |
78.57 |
|
7 |
13 |
17 |
76.47 |
|
8 |
15 |
21 |
71.42 |
|
9 |
11 |
11 |
100 |
Proceed as normal |