Project Milestone
Project Highlights
Iteration | Date | Features | Description | Action |
---|---|---|---|---|
4 | 6/11/2013 | Task Management | Lien Centre mentioned that they would not need this feature | Feature removed on 6/11/2013 |
4 | 7/11/2013 - 14/7/2013 | Create Event - Remove Event | Team members were too busy with school work and exams | Features postponed to Iteration 6 |
7 | 3/12/2013 | Name Card Reader | Lien Centre brought up a new idea, hoping to be included into our scope. We evaluated the complexity of the feature | Feature to be put on hold |
7 | 12/12/2013 | -- | Openshift problem. Deployed URL was down quite often | Resolved by redeploying after several attempts |
8 | 31/12/2013 | Email - Survey | Features could not be completed as most of the team members were overseas | Features rescheduled to later iterations |
9 | 28/1/2014 | Email - Feedback | Technology errors, hinders progress of the new features.Email unable to send and survey cant be customised. | PM decided to exclude both features for User Testing 1 |
9 | 28/1/2014 | Name Card Reader Tagging | Lien Centre proposed this feature again, hoping to include this feature in our project scope. Lien Centre proposed another feature, tagging | After consideration and consulting supervisor, PM decided to drop Publicity (Facebook + Twitter) feature, and accepted the 2 new features. Rescheduled |
10 | 4/2/2014 | User Interface | "After User Testing 1, we discovered a lot of problems with our interface | We decided to do a UI revamp. Rescheduled to have iteration 11 focused on UI revamp and integration, in preparation for mid terms |
12 | 21/2/2014 | Namecard Reader | As advised from reviewers on Mid Terms Presentation, and further discussion with supervisor, this feature is dropped for better focus on other features. | Feature dropped. |
12 | 21/2/2014 | Tagging | As advised from reviewers on Mid Terms Presentation, and further discussion with supervisor, this feature is dropped for better focus on other features. | Feature dropped |
13 | 11/3/2014 | User Testing 3 | Team decided to plan for the large scale User Testing 3 upon advice from Midterm presentation on the first week of April instead of end of March as planned as we felt that we are not ready with our development for this thorough User Testing. | User Testing 3 postponed to first week of April |
13 | 26/3/2013 | Analytics | "Upon discussing with the client, team has decided to place emphasis on the dashboard and analytics, improved the catering of needs to our client | Detailed discussion and concise plan with the client and team to understand their needs and concluding the usefulness of analytics and what is required. |
13 | 28/3/2013 | User Testing 2 | Team decided to conduct a small testing with other people, to foresee the problems that might occur or bugs that are unidentified before the large scale User Testing 3 | We found a few friends to do the testing, and did an internal review. |
14 | 4/4/2014 | User Testing 3 | A large scale User Testing, involving all our users, from Lien Centre staff to our friends, to facilitate the whole procedure of managing an event, from Registration to Analytical Summary, to gather feedback for the usage of the system LIVE. | User Testing 3 stretched over 8 days, with different activities taking place from first day to the last, ranging from creation of event with Lien Centre, Registration from public, doing survey and also event summary. |
Project Schedule
S/N | Description | Link |
---|---|---|
1 | Project Schedule | Download |
Current Iteration: Iteration 11 (7 Feb 2014 - 20 Feb 2014) - Functionalities #7
Status | Task Name | In Charge | Planned Start Date | Planned Finish Date | Days Planned | Actual Start Date | Actual Finish Date | Days Taken | |||
Project Requirement and Management | |||||||||||
COMPLETED | Final Presentation Preparations | Xiu Hao | 4-Apr-14 | 8-Apr-14 | 5 | 4-Feb-14 | 8-Feb-14 | 5 | |||
COMPLETED | User Testing 2 | Xiu Hao | 4-Apr-14 | 8-Apr-14 | 5 | 4-Apr-14 | 8-Apr-14 | 5 | |||
Integration | |||||||||||
Pending | Final Integration | Trinh | 4-Apr-14 | 17-Apr-14 | 14 | 4-Apr-14 | - | ||||
Testing | |||||||||||
Pending | Test all features | Thu | 17-Apr-14 | 17-Apr-14 | 1 | - | - | ||||
Pending | Debug | Jason | 17-Apr-14 | 17-Apr-14 | 1 | - | - |
Past Iteration Reports
Iteration | Download |
---|---|
Iteration 14 | |
Iteration 13 | |
Iteration 12 | |
Iteration 11 | |
Iteration 10 | |
Iteration 9 | |
Iteration 8 | |
Iteration 7 | |
Iteration 6 | |
Iteration 5 | |
Iteration 4 | |
Iteration 3 | |
Iteration 2 | |
Iteration 1 |