IS480 Team wiki: 2013T2 Invenio/Midterm
Home | Our Team | Project Overview | Project Management | Project Documentation | Learning Outcomes |
Project Progress Summary
Immediate Deliverables
Click here to view our mid-term presentation slides in PDF format
Click here to download our mid-term presentation in PPT version
Link to live web console: http://202.161.45.159:8080/
Our Key Accomplishments
- 81% of the Project Completed |
Project Timeline Overview
Project Highlights
#1 - The client had requested for additions to the scope which led to delays in iterations 6 and 7. This was unexpected as the requirements were different from what was originally discussed, and more importantly, the changes were raised during the "Loan Asset" iteration, when we have already begun working on the previous requirements. The mitigation plan was to increase our man-hours and we added 4 buffer days to accommodate this change.
#2 - The client has specifically requested for a new User Test 2 after User Test 1 within short notice. To accommodate that request, we have scheduled a second User Test 2 in Iteration 10.
Project Management
Project Status
In Summary
All functionalities in the Core and Secondary circles, except those highlighted in the red boxes have been successfully deployed and tested at both our Usability Tests. We have 3 more iterations to go before our final presentation. We are currently on schedule and we are confident that the project will progress as planned.
Click here to see a detailed description of all funtionalities.
Click here to download our full project schedule:
Invenio Project Schedule
Project Schedule (Plan Vs Actual)
Iteration | Task Name | Reason for the delay/push back | Mitigation |
---|---|---|---|
6 |
|
Complexity of requirements | Take up 2 buffer days and increase man-hours |
7 |
|
Complexity of requirements | Take up 2 buffer days and increase man-hours |
Project Metrics
This section reveals a summary of the schedule metrics and bug metrics derived over the past 10 iterations.
Click here to understand how we derive our metrics and what are the action plans to each metric.
Schedule Metrics
This chart shows an overview of the schedule metrics for our project over the past 10 iterations.
Key issues
Iteration 6: Iteration 6 was delayed by 2 days because of the complexity of the loan process, which requires 2 levels of approval before an asset can be loaned out. This additional level of approval was requested by the client. To accommodate this additional level, more work hours had to be allocated for programming work.
Iteration 7: Iteration 7 was also delayed by 2 days because of the complexity of the audit process, which requires multiple interactions (may be over the course of different days) between the web application and the mobile application. Coupled with the delayed iteration 6, iteration was subsequently pushed back by 2 days to accommodate the additional work involved.
Bug Metrics
The charts below show an overview of the bug metrics for our project over the past 10 iterations.
Bug Metric Table:
Bug Metric Summary:
Click here to download the full bug metric:
Project Risks
Top 3 Risks:
Click here for our detailed risk assessment measure:
Risk Assessment Measure
Technical Complexity
This section explains in detail the key indicators used to measure the quality of our system. These 3 qualities are - usability, flexibility and security.
Usability (Web Application)
- Allows user to view the selected image prior to upload
- Acts as a confirmation measure (What you see is what you’ll get)
- Prevents mistakes and reduces human error
- Allows user to monitor the progress of the audit at a glance
- Eliminates the need to track progress manually
- Reduces the workload of the user
Usability (Android Application)
Selective Display of Asset Details
Flexibility
Security
Quality of Product
Intermediate Deliverables
Stage | Specification | Links |
---|---|---|
Project Management | Metrics | |
Minutes | ||
Requirements | Prototypes | |
Analysis | Use Case | |
Design | Class Diagram | |
ER Diagram | ||
System Architecture Diagram | ||
System Sequence Diagram | ||
Sequence Diagrams | ||
Testing | Internal Test Plan | |
Internal Test cases and Results | ||
Usability Test 1&2 |
Deployment
The following is the Midterm deployed versions of both the web application and the Android application:
Link: [Web Application]
Link: [Android Application]
Login Credentials:
Username : generalEmp1
Password : test
Testing
We conducted 2 Usability Tests throughout the duration of our Project.
Click on the links below to find our more about the test, as well as test documentations and results.
User Test 1 - 24 January 2014 -> click here
User Test 2 - 7 February 2014-> click here
Reflection
Team Reflection
[[ | 400px]]