Project Review



It image2.jpg

Project Progress Chart


Click here to find out more about our mid-term progress.




NEWFYP2.PNG

Project Challenges


The client changed the scope of the project. For instance, the functionality of check-in counter, they client expect the team to go all the way down to the micro level (zooming into the number of desk that each check-in counter has, instead of just focusing on the macro level, such as the number of check-in counters.
Secondly, for the functionality of parking bay, CAG wants to view the percentage of the parking bay being utilized and break down into a stack chart. The team faced some issues such as the fact that many smaller flights can fit into the bigger parking bays.

Project Achievements


Successfully used C# language to code out the application for CAG. CAG users is happy with the functions. It helps the user to visualise the data in the easiest manner. For example, the check-in counter user wants to see the outliers, instead of the mean. The reason is that the user wants to see if there are many outliers or just one or two. If there are many outliers, they will focus more attention on it.
Integrating all the knowledge and software we have learnt in the school. For instance, we have use MSSQL 2005 server to store the database. To retrieve the data, we have used SSIS to assist us to generate the results.
Successfully make use of zedgraph to show the graph generated by the user input. For example, in the check-in counter function, by selecting the time frame and the terminal, the user could determine how many counters to open.

Project Video

Click here for our video!

Project Poster


Click here to view our poster!

Project Management

Project Schedule (Planned vs Actual)


It planned actual.jpg

Click here to find our more about our detailed schedule.

Task Delegation Tracker


Click here for our Task Delegation.

Change Management Tracker


Click here for our Change Management log.

Project Schedule (Current Iteration)


Click here to view our detailed schedule

Deployment


Dep.PNG

Project Metrics


Schedule Metrics
Ittt schedule.jpg

Click here for the schedule metric descriptions and the data collected.

Bug Metrics
Ittt bttt.jpg

Click here for the bug metric descriptions and the data collected.

Project Risks


It-top3risk.jpg

Final Presentation Slides

Click here to view our Final Presentation Slides

X Factor

Click here for details on our X Factor.

Quality of Product

Project Deliverables


Stage Specfication Modules
Project Management Minutes Supervisor Minutes, Client Minutes , Internal Minutes
Metrics Bug Metric , Schedule Metric
Requirements Scenario FlowChart Process FlowChart
Business FlowChart Business FlowChart Parking Bay Business Process, Check-in Counter Business Process
Analysis Use Case Use Case Diagram
UI Mockups View Flight Analysis, View Passenger Analysis, View Parking Bay Analysis, View Check-in Counter Analysis
Design System Architecture Diagram System Architecture Diagram
Entity Relationship Diagram Entity Relationship Diagram
ETL Diagram View Flight Analysis,View Passenger Flow Analysis,View Parking Bay Analysis,View Check-in Counter Analysis
Testing User Test Plan User Manual


User Test (UT)


User Test 1 (UT 1) Click here to view our 1st User Test with CAG.
User Test 2 (UT 2) Click here to view our 2nd User Test with CAG.

Project Reflection

Team Reflection

Teamref.PNG

Individual Reflections



Dang.PNG

Naren.PNG

Yinmon.PNG

Yc.PNG

Singhvi.PNG

Peter.PNG