S/N Milestone Dates
01
  • Project Acceptance Presentation
30 Dec 2010
02
  • Begin Formal Development
5 Jan 2011
03
  • End Iteration 1, INSG Alpha 1 Release
19 Jan 2011
04
  • End Iteration 2, INSG Alpha 2 Release
2 Feb 2011
05
  • End Iteration 3, INSG Alpha 3 Release
16 Feb 2011
06
  • End Iteration 4, INSG Beta 1 Release, Begin Testing Phase
2 Mar 2011
07
  • INSG Beta 2 Release, Deploy to Staging Server
18 Mar 2011