HeaderSIS.jpg

IS480 Team wiki: 2013T2 Silicon Geeks

From IS480
Jump to navigation Jump to search

Final logo.PNG

Home Team Description Project Overview Project Management Project Documentation Project Testing Key Milestones



Silicon Geeks Logo.png

Welcome to Team Silicon Geeks Wiki Page!

Man cannot discover new oceans unless he has the courage to lose sight of the shore.


Knowing the previous value of time, this has been the driving force for us to keep ourselves motivated, to strive to be the best that we can be. Now that our college life has almost come to an end, we believe that working closely with Sentosa can help us test our new acquire skills and put it into practice, to create something important, critical, and effective for Sentosa.


Stay hungry, stay foolish.



09/06/2014 – Sentosa Proposal Submission
Download:Sentosa Project Proposal

18/06/2014 – Proposal Submission
Download:Project Proposal

14/08/2014 – Acceptance Presentation
Acceptance Page

07/10/2014 – Midterm Presentation
Mid Term Wiki

10/11/2014 – Poster Submission
Download:Poster

02/12/2014 – Final Presentation
Finals Wiki

03/12/2014 – Poster Day


Current Iteration:
14

Final Presentation
Date Start: 28/11/2014
Date End: 03/12/2014
Duration:6 days

Features to complete :
-
- Preparation for presentation

Project Status for Iteration 13:
Schedule Metrics Score:
75%

Schedule Metrics Status:
Slightly behind time

Reason for Delay:
Printing Bugs found

Action-to-be-taken:
Inform supervisor. Used up buffer days

Bug Metrics Point:
-

Running Bug Point:
-

Action-to-be-taken:
-